Placer County, CA Parking Rules: EV Charging (2026)
Key Facts
- Deemed-complete window
- 5 business days (10 if >25 stations)
- Deemed-approved window
- 20 business days (40 if >25 stations)
- HOA approval
- Cannot be required absent safety finding
- Appeal body
- Planning commission / Building Board of Appeals
- Appeal window
- 30 days from building official's decision
- Governing statute
- Implements Gov. Code § 65850.7
Summary
Placer County Code § 15.04.160 sets an expedited, deemed-approved permit process for electric vehicle charging stations. An application is deemed complete after five business days (10 for more than 25 stations at one site) without a correction notice, and deemed approved, with all permits issued, after 20 business days (40 for more than 25 stations) unless the building official finds a specific adverse health or safety impact.
"Electric vehicle charging station" or "charging station" means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this chapter, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle... Twenty business days after the application was deemed complete, if the application is for at least 1, but not more than 25 electric vehicle charging stations at a single site. Forty business days after the application was deemed complete, if the application is for more than 25 electric vehicle charging stations at a single site.
Full Breakdown
160 requires the building official to run an expedited administrative review for any electric vehicle supply equipment built to Article 625 of the California Electrical Code that delivers power into a plug-in vehicle. The county must publish an adopted checklist on its website, accept electronic submittals including e-mail, internet, or fax, and take electronic signatures. An application is deemed complete once five business days pass (10 business days for more than 25 charging stations at one site) without the building official either deeming it complete or issuing a written correction notice detailing every deficiency.
Once complete, the application is deemed approved and all necessary permits issue automatically after 20 business days (40 business days for more than 25 stations) unless the building official has affirmatively approved it, found based on substantial evidence that the installation could have a specific adverse impact on public health or safety, or denied it because no feasible mitigation exists; an appeal to the planning commission also pauses deemed approval. The building official cannot condition approval on a homeowners' association's sign-off unless that same adverse-impact finding is made.
A building official's decision may be appealed to the Building Board of Appeals within 30 days. Approval of the permit itself does not authorize energizing the station: separate authorization from the county is still required before use.
Violations & Fines
Energizing or using an approved electric vehicle charging station before the county grants separate authorization to do so is not permitted under § 15.04.160(F)(4)(c). Because the underlying installation is regulated as electrical work, unpermitted charging stations fall under the building code's general violation provisions in § 15.04.140: a misdemeanor (or infraction for a first offense under County Code § 1.24.010), with each day of continued violation a separate offense.
Frequently Asked Questions
How long does Placer County take to approve an EV charging station permit?
Can my homeowners' association block my EV charger permit?
Can I use my EV charger as soon as the permit is approved?
Sources & Official References
Other rules in Placer County