Kern County, CA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified June 2026

Key Facts

Permit type
Ministerial building permit
Deemed complete
5-10 business days
Deemed approved
20-40 business days after completeness
Review scope
Health and safety only
HOA approval condition
Prohibited

Summary

California law requires Kern County to approve applications to install electric vehicle charging stations administratively through a nondiscretionary building permit, limits county review to health and safety requirements, and deems applications complete or approved if the county misses statutory deadlines.

City-specific rules exist: Ridgecrest, and Bakersfield have their own ev charging rules that differ from Kern County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

(b) (1) A city, county, or city and county shall administratively approve an application to install electric vehicle charging stations through the issuance of a building permit or similar nondiscretionary permit. ... (3) Review of an application to install an electric vehicle charging station or hydrogen-fueling station shall be limited to the building official's review of whether it meets all health and safety requirements of local, state, and federal law. The requirements of local law shall be limited to those standards and regulations necessary to ensure that the electric vehicle charging station or hydrogen-fueling station will not have a specific, adverse impact upon the public health or safety. However, if the building official of the city, county, or city and county makes a finding, based on substantial evidence, that the electric vehicle charging station or hydrogen-fueling station could have a specific, adverse impact upon the public health or safety, the city, county, or city and county may require the applicant to apply for a use permit. ... (g) (1) (A) On or before September 30, 2016, every city, county, or city and county with a population of 200,000 or more residents, and, on or before September 30, 2017, every city, county, or city and county with a population of less than 200,000 residents, shall, in consultation with the local fire department or district and the utility director, if the city, county, or city and county operates a utility, adopt an ordinance, consistent with the goals and intent of this section, that creates an expedited, streamlined permitting process for electric vehicle charging stations. ... (h) A city, county, or city and county shall not condition approval for any electric vehicle charging station or hydrogen-fueling station permit on the approval of the station by an association, as that term is defined in Section 4080 of the Civil Code.

Full Breakdown

Government Code Section 65850.7 declares EV charging station permitting a matter of statewide concern and requires every city and county, including Kern County's unincorporated areas, to approve EV charging station applications ministerially through a building permit or similar nondiscretionary permit, with review limited to health and safety. Under subdivision (g), counties with 200,000 or more residents had to adopt an expedited, streamlined EV charging permitting ordinance with a published checklist by September 30, 2016. Under Government Code Section 65850.71 (AB 970), an application is deemed complete if the county takes no action within 5 business days (1-25 stations at a site) or 10 business days (more than 25), and deemed approved 20 or 40 business days after completeness, respectively, absent specific health and safety findings. Approval may not be conditioned on homeowners association consent.

Violations & Fines

These are state mandates on the county rather than restrictions on residents: if Kern County fails to act within the statutory timeframes, an EV charging station application is deemed complete and ultimately deemed approved by operation of law (Government Code Section 65850.71).

Frequently Asked Questions

Can Kern County require a use permit for my home EV charger?
Only if the building official makes a finding, based on substantial evidence, that the charging station could have a specific, adverse impact on public health or safety. Otherwise approval must be administrative and nondiscretionary.
How fast must Kern County act on an EV charger permit application?
Under Government Code Section 65850.71, applications for up to 25 stations are deemed complete after 5 business days of county inaction and deemed approved 20 business days after completeness; larger projects get 10 and 40 business days.
Does this state law apply in unincorporated Kern County?
Yes. Section 65850.7 applies to every city, county, and city and county in California, and the Legislature declared EV charging permitting a matter of statewide concern rather than a municipal affair.

Sources & Official References

Other rules in Kern County

All Kern County rules

California rules heatmap·Compare Kern County to another location·View the California parking rules overview

Get notified when EV Charging in Kern County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Cities Across Kern County