Citrus County, FL Parking Rules: Loading Zones (2026)
Key Facts
- Governing instrument
- Land Development Code Ch. 7, Sec. 7290
- Applies to
- Unincorporated Citrus County only
- Small-truck bay size
- 10 ft by 20 ft (up to 2 tons)
- Large-truck bay size
- 12 ft by 60 ft (over 2 tons)
- Prerequisite for
- Certificate of Compliance / Business Tax Receipt
- Ordinance date
- Ord. 2025-A04, March 11, 2025
Summary
In unincorporated Citrus County, every commercial and industrial building must provide off-street loading space sized to the delivery trucks it expects, and the space has to be built and usable before the county will issue a Certificate of Compliance or Local Business Tax Receipt.
A. The off-street loading requirements of this section are intended to provide minimum standards necessary for loading and unloading of goods for the various commercial and industrial uses permitted by this chapter to protect the capacity of the County's street system, to avoid undue congestion resulting from loading and unloading activities, and to lessen unnecessary conflicts between trucks and other vehicles. B. Requirements of this section shall apply to all commercial and industrial development... Off-street loading shall be available for use prior to issuance of any Certificate of Compliance or Local Business Tax Receipt... No off-street loading shall be altered or discontinued except in accordance with this chapter. C. Loading spaces shall not be used for storage of vehicles and/or materials; loading spaces shall not be used to meet off-street parking requirements. G. 1. Trucks not exceeding two tons in load capacity - 10 feet by 20 feet. 2. Trucks exceeding two tons in load capacity - 12 feet by 60 feet.
Full Breakdown
Land Development Code Sec. 7290 (Chapter 7, Transportation Systems Standards, adopted by Ord. 2025-A04, effective March 11, 2025) sets the off-street loading standards for unincorporated Citrus County; Crystal River and Inverness apply their own separate codes inside city limits. The rule applies to all commercial and industrial development, new or altered. Loading space must be available for use before the county issues a Certificate of Compliance or Local Business Tax Receipt, and the property owner and occupant must keep it maintained for as long as the use needing it continues; loading facilities cannot be altered or discontinued except as the chapter allows.
Loading spaces cannot double as vehicle or material storage, and they cannot be counted toward a site's separate off-street parking requirement. Space count is tied to gross floor area and varies by use classification (financial institutions and hotel/motel uses get one space for the first 75,000 square feet plus one for each additional 25,000 square feet; industrial uses get one space for 5,000 to 20,000 square feet plus one for each additional 20,000 square feet), with offices and general commercial uses following their own bracket in the same schedule.
Every loading space must be striped and marked. Minimum bay size depends on the delivery trucks the site expects: 10 feet by 20 feet where deliveries run in trucks up to two tons, and 12 feet by 60 feet where deliveries run in heavier trucks. Larger projects must submit a delivery-truck turning-movement analysis using the largest truck expected to visit the site. Loading areas must sit on the same building site as the use they serve, outside rights-of-way, and must be buffered from any abutting residential use under the LDC's buffer standards.
Violations & Fines
A site cannot obtain its Certificate of Compliance or Local Business Tax Receipt until the required loading space is built and available for use, so noncompliance blocks occupancy and business licensing outright. Using a loading space for parking, storage of vehicles, or material storage, or altering or discontinuing loading facilities outside the chapter's terms, is itself a violation the county can enforce under its code enforcement process (Chapter 19).
Frequently Asked Questions
Does this loading-space rule apply inside Crystal River or Inverness?
How big does a loading space have to be?
Can a business use its loading space for extra parking?
When must the loading space be built?
Sources & Official References
Other rules in Citrus County
Florida rules heatmap·Compare Citrus County to another location·View the Florida parking rules overview