Solano County, CA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit authority
County transportation director
Permit revocation notice
5 days
Work completion window
6 months from issuance
Bond release timeline
90 days after completion
Utility relocation notice
30 days

Summary

Building or placing anything, including a sidewalk, driveway, fence or wall, in or over a county road right-of-way in unincorporated Solano County requires an encroachment permit from the transportation director first. Permits can be revoked on five days' notice and the permittee must restore the road at their own expense when the work is done.

City-specific rules exist: Vacaville, Vallejo, and Fairfield have their own encroachment permits rules that differ from Solano County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

It shall be unlawful for any person to construct, maintain, make, place or install any encroachment along or on any county road without first obtaining a permit to do so in the manner herein provided.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 1868, passed April 9, 2026).

Full Breakdown

Solano County Code Chapter 24, Article I defines and regulates encroachments on county roads. Section 24-10 defines an encroachment broadly to include a tower, pole, pipeline, driveway, private road, curb and gutter, sidewalk, fence, wall, billboard, stand, building, structure, tree, shrub or any other object placed in, under or over a county road, and separately confirms that a driveway connecting a county road to abutting property counts as an encroachment requiring its own permit for public safety. Section 24-11 makes it unlawful to construct, maintain, make, place or install any encroachment on a county road without first obtaining a permit, with a narrow emergency exception for urgent repairs to existing utility lines, provided the person applies for a permit within a reasonable time afterward.

Applications go to the director of the transportation department under Section 24-12 and must identify the applicant, the type and location of the proposed encroachment, and its proposed duration, along with any plans or sketches the director requires. The permittee bears the entire cost of restoring the county road to its prior condition, and a fee is charged per the board of supervisors' adopted fee schedule. Most permits are revocable on five days' notice, work must be completed within six months of issuance (extendable by the director), and utility or public-agency permits can be required to relocate facilities on thirty days' notice if road improvements need the space.

Section 24-13 lets the director require a cash deposit, certified check or surety bond sized to cover restoring the road if the permittee defaults, released ninety days after satisfactory completion. Section 24-14 requires the permittee to provide lights, barriers, warning signs and other safeguards for public safety during the work and to restore the roadway as nearly as possible to its original condition once finished.

Violations & Fines

Constructing, maintaining or installing a sidewalk, driveway, fence, wall or other encroachment on a county road without a permit is unlawful under Section 24-11(a). The transportation director can cancel a noncompliant permit and restore the right-of-way at the permittee's expense under Section 24-14(b) if required safeguards are not provided after notice, and most permits remain revocable on five days' notice under Section 24-12(f).

Frequently Asked Questions

Do I need a permit to put a driveway or sidewalk on a Solano County road right-of-way?
Yes. Section 24-10 defines a driveway and a sidewalk as encroachments, and Section 24-11 makes it unlawful to construct, place or install any encroachment on a county road without first getting a permit from the county transportation director.
How long do I have to finish work under a Solano County encroachment permit?
Six months from the date of issuance under Section 24-12(h). The transportation director can grant a reasonable extension, but if the work is not finished within that window, the permit becomes void and the permittee must restore the road to its original condition.
Can Solano County revoke my encroachment permit?
Yes, for most permit holders. Section 24-12(f) makes permits other than those held by public agencies or utilities revocable on five days' notice, at which point the director can require the encroachment to be removed or relocated.

Sources & Official References

Other rules in Solano County

All Solano County rules

California rules heatmap·Compare Solano County to another location·View the California sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Solano County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Cities Across Solano County