Minnehaha County, SD Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing ordinance
MC #47-15
Permitting authority
County Highway Superintendent
Appeal window
5 working days
Appeal body
County Commission
Fee waiver
Public government applicants exempt
Bond
May be required as permit condition

Summary

Anyone installing, relocating or expanding a utility facility in a Minnehaha County highway right-of-way must first get a permit from the County Highway Superintendent under Ordinance MC #47-15. The Superintendent can grant, condition, deny or revoke the permit, and public government applicants pay no fee.

City-specific rules exist: Sioux Falls has its own encroachment permits rules that differ from Minnehaha County's county-level regulations. If you live in Sioux Falls, check the city-specific page instead.

Before the installation, relocation, or expansion of any utility facility may be made within any highway right of way under the jurisdiction of the County, the owner of a utility shall submit an application to the County Highway Superintendent for a utility permit allowing for such installation, improvement, maintenance, relocation, or expansion.

Full Breakdown

Ordinance MC #47-15, the Highway Utility Crossing Ordinance, controls any encroachment into a county highway right-of-way by a "utility facility," a term the ordinance defines broadly to cover electric power, communications, cable television, water, gas, oil, slurry, petroleum products, steam, sanitary sewers, wireless towers, and public or private drainage or irrigation lines. Section 3(a) requires the utility owner to submit an application to the County Highway Superintendent before any installation, improvement, maintenance, relocation, or expansion within a right-of-way under county jurisdiction, using a form the Superintendent promulgates under Section 2.

The Superintendent may grant a permit outright, grant it with modifications or conditions, or deny it, based on the ordinance and criteria compiled in a policy guidebook filed with the County Auditor and Highway Department (Section 2(c)). Any work must follow the permit's conditions exactly, and the Superintendent may revoke a permit on a written finding that permit conditions or the underlying criteria have been violated (Section 3(d)). Section 4 lets the Superintendent set and publish a permit fee in the criteria guidebook; no application can be approved until that fee is paid, though the fee is waived entirely for "public government applicants," defined in Section 1(c) as the United States government, the State of South Dakota, and municipalities, counties, and townships.

Section 5 allows the Superintendent to require a performance bond as a condition of the permit if not already required by other law. An applicant or permit holder who disagrees with a grant-with-conditions, denial, or revocation decision has five working days from the Superintendent's decision to file a written appeal with the County Auditor, the Highway Superintendent, and the County Commission Office; the Commission then hears the appeal at a regular meeting and reviews the Superintendent's decision for abuse of discretion, voting to uphold, uphold with modification, or reverse it.

Violations & Fines

Working in a county right-of-way without an approved MC #47-15 permit, or outside the conditions of an issued permit, exposes the utility owner to permit revocation once the Superintendent makes a written finding of a violation. There is no separate fine schedule in the ordinance itself; enforcement runs through permit denial, revocation, and the County Commission's appeal process rather than criminal citation.

Frequently Asked Questions

Who issues a utility right-of-way permit in Minnehaha County?
The County Highway Superintendent, acting under Ordinance MC #47-15, reviews and issues permits for any utility facility installed, relocated, maintained, or expanded within a highway right-of-way the county controls, using criteria compiled in a guidebook filed with the County Auditor.
Can the county revoke a right-of-way permit after it's issued?
Yes. Section 3(d) lets the Superintendent revoke a permit on a written finding that the permit's criteria, rules, or conditions were violated or not fulfilled, effectively halting further work in the right-of-way.
How do I appeal a denied or revoked utility permit?
Section 3(e) gives you five working days from the Superintendent's decision to file written notice of appeal with the County Auditor, Highway Superintendent, and County Commission Office; the Commission then reviews the decision for abuse of discretion at a regular meeting.
Do government entities pay the utility permit fee?
No. Section 4(c) waives the permit fee for public government applicants, defined as the United States government, State of South Dakota, and municipalities, counties, and townships applying for a permit.

Sources & Official References

Other rules in Minnehaha County

All Minnehaha County rules

Compare Minnehaha County to another location·View the South Dakota sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Minnehaha County, SD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Cities Across Minnehaha County