Key Facts

Governing chapter
County Code Chapter 72
Permit issued by
County Engineer
Initial application fee
$100
Late/no-permit fee
$250
Max fine
$1,000 per offense/day
Appeal window
5 business days

Summary

Digging into, opening, or placing anything within a County road or right-of-way in Atlantic County requires a written permit from the County Engineer before work starts. Chapter 72 covers excavations, structures, and other private encroachments on County highways and drainage easements, and violators face disorderly-persons fines up to $1,000 per day.

These county ordinances apply to unincorporated areas of Atlantic County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

It shall be unlawful for any person or persons, firm, corporation, charitable organization, nonprofit entity, municipality, public or private utility or other entity to perform any of the following acts within, upon or under any County road or right-of-way, without first obtaining a written approved permit from the office of the County Engineer as hereafter provided:

A. To make any excavation in, or to open, alter, or tear up the surface of any County right-of-way for any purpose whatsoever; regardless of whether the activity is occurring in an area that is paved or unimproved by the County, and regardless of the duration of the activity;

B. To make any excavation in, or fill, alter, connect to, or otherwise damage any portion of any stormwater drainage easement or stormwater drainage improvement that is owned, maintained, or controlled by the County, for any purpose whatsoever;

C.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4863463; v25 updated 2026-04-21; through 04-21-2026).

Full Breakdown

Atlantic County Code Chapter 72, adopted September 5, 2023 by Ordinance No. 10-2023, makes it unlawful to excavate, open, or otherwise disturb a County road or right-of-way, or to place a structure, fixture or improvement in one, without first getting a written highway occupancy permit from the County Engineer (Section 72-3). O. , Monday through Friday, excluding County holidays (Section 72-6A). The property owner benefiting from the work must sign the application even if a contractor is doing the digging, and the plan set must show right-of-way dimensions, existing utilities, drainage structures, and engineering details, prepared by a licensed New Jersey engineer or surveyor when the County Engineer requires it (Section 72-6B-C).

Every applicant pays a $100 initial application fee plus a permit fee set by the county's Schedule A, and fees are never refunded once paid (Section 72-7A, C). Starting work in the right-of-way without a permit triggers a stop-work order and a $250 late-processing assessment on top of the standard fees (Section 72-7D). Government agencies and nonprofits skip the fee but still need a full application and a performance and maintenance guarantee under Section 72-8. If the permittee fails to restore a disturbed area, the County repairs it and bills the permittee, and can sue for the balance after 30 days (Section 72-18D).

Violations & Fines

Working in a County right-of-way without a permit, or violating any Chapter 72 requirement, is a disorderly-persons offense under N.J.S.A. 40:24-2, punishable by a fine of up to $1,000 per offense; each day a violation continues counts as a separate offense (Section 72-18A). A denied applicant may appeal in writing to the County Engineer within five business days; the Permit Appeal Committee, made up of two Engineering Division representatives and one from the Legal Department, must meet within 10 business days and decide within 45 calendar days (Section 72-19).

Frequently Asked Questions

Do I need a permit to dig in an Atlantic County right-of-way?
Yes. Section 72-3 of the County Code makes it unlawful to excavate, open, or disturb any County road or right-of-way for any purpose, or to place a structure or fixture there, without first getting a written highway occupancy permit from the County Engineer. This applies regardless of whether the area is paved, and no matter how short the work will take.
How much does an Atlantic County right-of-way permit cost?
Every application requires a $100 initial application fee plus a separate permit fee set by the county's Schedule A fee schedule. Fees are non-refundable once paid. If work starts before a permit is issued, the County adds a $250 late-processing assessment on top of the regular fees, in addition to any penalties assessed under Chapter 72.
What happens if I work in the right-of-way without a permit?
It is a disorderly-persons offense under N.J.S.A. 40:24-2, punishable by a fine of up to $1,000 per offense, with each day the violation continues treated as a separate offense. The County Engineer can also issue a stop-work order, and if you fail to restore the site the County will do the repairs and bill you for the cost.

Sources & Official References

Other rules in Atlantic County

All Atlantic County rules

Compare Atlantic County to another location·View the New Jersey sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Atlantic County, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Cities Across Atlantic County