Butte County, CA Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Tier 1 permit
Building permit only, by right
Tier 2 permit
Administrative Permit
Tier 3 permit
Minor Use Permit
Tier 4 permit
Conditional Use Permit
Roof panel height cap
6 ft above roofline (12 ft w/ MUP)
Abandonment trigger
24 months without power production

Summary

Butte County sorts solar installations into four Utility land-use tiers, from a by-right building permit for rooftop and small ground systems up to a Conditional Use Permit for major ground-mounted power plants, each with its own height and setback table.

City-specific rules exist: Chico has its own panel permits rules that differ from Butte County's county-level regulations. If you live in Chico, check the city-specific page instead.

Utilities, Minor. Utility facilities that are necessary to support on-site development on the same parcel that involves only minor structures. Examples of Utilities, Minor include Tier 1 Solar Energy Facilities, Auxiliary Rooftop and Micro Wind Energy Systems, power lines, water and sewer lines, water transmission lines, storm drainage facilities, transformers, and water and sewer pump stations. Utilities, Minor includes uses are permitted by right with a building permit in all zones.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 61).

Full Breakdown

Section 24-157 classifies solar under four Utility land-use types tied to Table 24-157-1. Utilities, Minor covers Tier 1 systems, roof-mounted or ground-mounted up to one-half acre, and per the glossary definition these are permitted by right with a building permit in all zones. Utilities, Accessory covers Tier 2 systems, ground-mounted and limited to less than 15 percent of the parcel up to 5 acres, whichever is less, with less than 50 percent of power used off-site; these require an Administrative Permit in most zones. Utilities, Intermediate covers Tier 3 systems, limited to less than 30 percent of the parcel up to 20 acres with 50 percent or more of the power used on-site, and needs a Minor Use Permit in most zones.

Utilities, Major covers Tier 4 systems, ground-mounted for off-site power generation, and requires a Conditional Use Permit in most zones. Tiers 3 and 4 in Agriculture zones are further restricted to Grazing Land or Other Land under the state Farmland Mapping and Monitoring Program and cannot sit on land under an active Williamson Act contract. Section 24-157(C) layers on engineering standards regardless of tier: photovoltaic systems must meet National Electrical Code, IEEE, and Public Utilities Commission safety and reliability standards, and ground-mounted systems must meet the applicable zone's setbacks.

Table 24-157-2 sets dimensional limits by parcel size: under 2 acres caps height at 8 feet with the zone's standard setback; 2 to 10 acres allows 10 feet with 10 additional feet of setback near residential zones; over 10 acres allows 15 feet with 15 additional feet of setback near residential zones. Roof-mounted panels are capped at six feet above the roof's maximum elevation unless a minor use permit approves up to twelve feet.

Violations & Fines

Installing a Tier 2, 3 or 4 system without the Administrative, Minor Use, or Conditional Use Permit its tier requires is a zoning violation the county can pursue through code enforcement, and an abandoned Solar Energy Facility, one that stops producing power on a continuous basis for 24 months without a showing of intent to continue, must have its equipment removed and the site restored under Section 24-157(C)(7).

Frequently Asked Questions

Do I need a permit for rooftop solar panels in Butte County?
Rooftop or small ground-mount systems classified as Tier 1, Utility Minor, are permitted by right with a building permit in all zones per Section 24-157 and the Utilities, Minor definition, so no discretionary land-use permit is required.
How tall can a ground-mounted solar array be on my parcel?
Table 24-157-2 caps height at 8 feet on parcels under 2 acres, 10 feet on parcels of 2 to 10 acres, and 15 feet on parcels over 10 acres, with extra setback required near residential zones as the parcel size increases.
What permit does a large commercial solar farm need?
A Tier 4 ground-mounted system delivering most of its power off-site is classified as Utilities, Major and requires a Conditional Use Permit in most zones, and in Agriculture zones is restricted to Grazing Land or Other Land not under a Williamson Act contract.

Sources & Official References

Other rules in Butte County

All Butte County rules

California rules heatmap·Compare Butte County to another location·View the California solar energy overview

Get notified when Panel Permits in Butte County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Panel Permits in Cities Across Butte County