Key Facts

Fee per solar collector panel
$3.50 each
Fee per storage tank
$17.50 each
Minimum mechanical/gas permit fee
$50.00
Late-start penalty
100% of the normal permit fee
Permit validity
18 months from issuance
Governing section
Clayton County Code § 18-47(d)(3)e

Summary

Unincorporated Clayton County requires a mechanical permit before installing solar collectors, charged under the county's per-unit fee schedule. Solar collector panels cost $3.50 each and storage tanks $17.50 each, on top of the $50.00 minimum mechanical and gas permit fee set in Section 18-47.

These county ordinances apply to unincorporated areas of Clayton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any owner, authorized agent, or contractor who desires to... erect, install, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes...he/she shall first make application to the county official and obtain the required permit for the work. ... e.Solar systems: .....1.Solar collectors, per panel .....$3.502.Storage tanks, each unit .....17.50

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 104).

Full Breakdown

Solar panels fall under the mechanical and gas permit fee schedule in Clayton County Code § 18-47(d)(3)e, which lists 'Solar systems: 1. 50 2. 00 for the third re-inspection under § 18-47(d)(3)b. Before work starts, § 18-41(a) requires the owner, agent or contractor to apply to the county official and obtain a permit for any mechanical system 'the installation of which is regulated by the construction codes'; the exceptions list in that same section covers items like portable heating and cooling equipment, but does not exempt solar collector arrays, so a rooftop or ground-mounted system needs its own permit.

Anyone who starts work before the permit is issued is charged a 100 percent penalty on top of the regular fee under § 18-47(b). Once issued, the permit is valid for 18 months and must show its first recorded inspection within six months or it lapses under § 18-46(a); the county official may grant extensions of up to 180 days on written request showing justifiable cause. The county official may inspect the installation at any stage under § 18-48(a) and can issue a stop-work order under § 18-33 if work proceeds contrary to the construction codes or in an unsafe manner, effective immediately upon written notice to the owner or the person doing the work.

Violations & Fines

Starting solar installation work before the permit is issued adds a penalty equal to 100 percent of the normal permit fee under § 18-47(b). A stop-work order under § 18-33 halts work immediately once the county official finds it noncompliant or unsafe, and the county official can revoke the permit under § 18-34 for a false statement on the application or for work that violates the construction codes.

Frequently Asked Questions

Do I need a permit to install solar panels in unincorporated Clayton County?
Yes. Section 18-41(a) requires an application and permit for any mechanical system installation regulated by the construction codes, and the fee schedule in Section 18-47(d)(3)e specifically lists solar collectors and storage tanks, confirming solar arrays are treated as a permitted mechanical installation rather than exempt work.
How much does a solar panel permit cost in Clayton County?
The county charges $3.50 per solar collector panel and $17.50 per storage tank under Section 18-47(d)(3)e, in addition to the $50.00 minimum mechanical and gas permit fee required for any mechanical permit under Section 18-47(d)(3)a. Re-inspections add $25.00 for the first visit, $50.00 for the second, and $100.00 for the third.
What happens if I install solar panels without a permit first?
The county adds a penalty equal to 100 percent of the usual permit fee for any work commenced before a permit is issued under Section 18-47(b), and the county official can issue a stop-work order under Section 18-33 requiring all work to cease immediately until the permit is obtained.

Sources & Official References

Other rules in Clayton County

All Clayton County rules

Compare Clayton County to another location·View the Georgia solar energy overview

Get notified when Panel Permits in Clayton County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.