St. Tammany Parish, LA Solar Energy: Panel Permits (2026)
Key Facts
- Governing section
- UDC Sec. 400-8(OO)
- Applies to
- medium- and large-scale ground-mounted systems
- Review fee
- $50 per acre, capped at $10,000
- Permit validity
- expires in 5 years
- Extension available
- one 2-year extension, good-faith proof required
- Site plan requirement
- stamped by a civil engineer
Summary
Ground-mounted solar systems bigger than small-scale in unincorporated St. Tammany Parish need a dedicated development-plan permit under UDC Sec. 400-8(OO), with a civil-engineer-stamped site plan, a $50-per-acre review fee capped at $10,000, and compliance with Chapter 300 building permit rules. Rooftop, building-mounted, and small-scale systems stay under standard zoning and building-permit review instead of this process.
4.Submission Requirements.a.All applications for ground-mounted solar energy systems exceeding small-scale systems, including medium-scale and large-scale facilities shall provide a scaled site plan stamped by a civil engineer including the location of all existing and proposed structures, points of ingress and egress, including internal circulation and parking and a traffic plan for construction.b.The applicant shall comply with all permit requirements as provided for within Chapter 300 - Buildings and Construction.c.Permit applications shall adhere to parish fees as listed within Article XVII - Parish Fees and shall also incur the following review fee: $50.00 per acre; maximum acreage fee $10,000.00.g.Any permit issued pursuant to this section will expire five years from the date of issuance, unless construction has commenced. The permit holder may apply to the director of permits and inspections for one extension of up to two additional years upon written demonstration of good-faith progress toward construction.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 12 Update 2).
Full Breakdown
Sec. 400-8(OO) of the parish's Unified Development Code creates a dedicated permitting track for ground-mounted solar energy systems that exceed "small-scale," meaning medium-scale (over 1,750 square feet of collector surface) and large-scale (over 40,000 square feet) arrays; systems that are building-integrated, building-mounted, roof-mounted, or classified as small-scale instead stay under ordinary building, electrical, and zoning compliance.
An application for a covered ground-mounted system must include a scaled site plan stamped by a civil engineer showing every existing and proposed structure, points of ingress and egress, internal circulation, parking, and a construction traffic plan. The applicant must also comply with all Chapter 300 building-permit requirements, and civil plans submitted for review must carry a Louisiana-licensed engineer's stamp. Beyond the standard parish fee schedule in Article XVII, the code layers on a review fee of $50.00 per acre, capped at a maximum of $10,000.00 regardless of project size.
Once issued, a solar permit is not open-ended: it expires five years after issuance unless construction has already begun. A permit holder facing delay can apply to the director of permits and inspections for a single extension of up to two additional years, but only on written proof of good-faith progress, such as an active utility-interconnection application, a signed power purchase agreement, or comparable evidence the project is moving forward. If the permit lapses without an extension, the applicant has to reapply from scratch. The same section separately sets a 15-foot maximum panel height, a 100-foot perimeter setback with a 50-foot natural buffer inside it, and a 300-foot separation from existing residential dwellings for the underlying ground-mounted system itself.
Violations & Fines
A permit that expires without construction underway, and without an approved extension, requires the applicant to start the application over rather than resume work. Building without the required Chapter 300 permit and Sec. 400-8(OO) site-plan approval exposes the project to stop-work action from the Department of Permits and Inspections, and an as-built plan must still clear engineering review before any certificate of occupancy issues.
Frequently Asked Questions
Do I need a special permit for a home rooftop solar system in St. Tammany Parish?
How much does a solar permit review cost in the parish?
How long is a St. Tammany Parish solar permit good for?
Sources & Official References
Other rules in St. Tammany Parish
Compare St. Tammany Parish to another location·View the Louisiana solar energy overview