Butte County, CA Solar Energy: Panel Permits (2026)
Key Facts
- Tier 1 permit
- Building permit only, by right
- Tier 2 permit
- Administrative Permit
- Tier 3 permit
- Minor Use Permit
- Tier 4 permit
- Conditional Use Permit
- Roof panel height cap
- 6 ft above roofline (12 ft w/ MUP)
- Abandonment trigger
- 24 months without power production
Summary
Butte County sorts solar installations into four Utility land-use tiers, from a by-right building permit for rooftop and small ground systems up to a Conditional Use Permit for major ground-mounted power plants, each with its own height and setback table.
Utilities, Minor. Utility facilities that are necessary to support on-site development on the same parcel that involves only minor structures. Examples of Utilities, Minor include Tier 1 Solar Energy Facilities, Auxiliary Rooftop and Micro Wind Energy Systems, power lines, water and sewer lines, water transmission lines, storm drainage facilities, transformers, and water and sewer pump stations. Utilities, Minor includes uses are permitted by right with a building permit in all zones.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 61).
Full Breakdown
Section 24-157 classifies solar under four Utility land-use types tied to Table 24-157-1. Utilities, Minor covers Tier 1 systems, roof-mounted or ground-mounted up to one-half acre, and per the glossary definition these are permitted by right with a building permit in all zones. Utilities, Accessory covers Tier 2 systems, ground-mounted and limited to less than 15 percent of the parcel up to 5 acres, whichever is less, with less than 50 percent of power used off-site; these require an Administrative Permit in most zones. Utilities, Intermediate covers Tier 3 systems, limited to less than 30 percent of the parcel up to 20 acres with 50 percent or more of the power used on-site, and needs a Minor Use Permit in most zones.
Utilities, Major covers Tier 4 systems, ground-mounted for off-site power generation, and requires a Conditional Use Permit in most zones. Tiers 3 and 4 in Agriculture zones are further restricted to Grazing Land or Other Land under the state Farmland Mapping and Monitoring Program and cannot sit on land under an active Williamson Act contract. Section 24-157(C) layers on engineering standards regardless of tier: photovoltaic systems must meet National Electrical Code, IEEE, and Public Utilities Commission safety and reliability standards, and ground-mounted systems must meet the applicable zone's setbacks.
Table 24-157-2 sets dimensional limits by parcel size: under 2 acres caps height at 8 feet with the zone's standard setback; 2 to 10 acres allows 10 feet with 10 additional feet of setback near residential zones; over 10 acres allows 15 feet with 15 additional feet of setback near residential zones. Roof-mounted panels are capped at six feet above the roof's maximum elevation unless a minor use permit approves up to twelve feet.
Violations & Fines
Installing a Tier 2, 3 or 4 system without the Administrative, Minor Use, or Conditional Use Permit its tier requires is a zoning violation the county can pursue through code enforcement, and an abandoned Solar Energy Facility, one that stops producing power on a continuous basis for 24 months without a showing of intent to continue, must have its equipment removed and the site restored under Section 24-157(C)(7).
Frequently Asked Questions
Do I need a permit for rooftop solar panels in Butte County?
How tall can a ground-mounted solar array be on my parcel?
What permit does a large commercial solar farm need?
Sources & Official References
Other rules in Butte County