McHenry County, IL Solar Energy: Panel Permits (2026)
Key Facts
- Inverter standard
- UL 1741 listed and labeled
- Ground-mount fire separation
- 7 feet from other structures
- Roof load design
- Two load cases under R324.4.1
- Design standard
- McHenry County UDO and NFPA 70
- Permit route
- Standard IRC building permit
- Effective date
- January 1, 2023
Summary
Rooftop and ground-mounted solar panels in unincorporated McHenry County are permitted under the county's amended 2021 International Residential Code, not through a separate solar-only process. Photovoltaic systems must use UL 1741-listed inverters, meet roof-load engineering for the added panel weight, and keep ground-mounted arrays at least 7 feet from any other structure.
R324.3 Photovoltaic systems. Photovoltaic systems shall be designed and installed in accordance with the McHenry County Unified Development Ordinance, Sections R324.3.1 through R324.7.2.5 and NFPA 70. Inverters shall be listed and labeled in accordance with UL 1741. Systems connected to the utility grid shall use inverters listed for utility interaction. ... R324.4.1 Roof load. ... Roof structures that provide support for photovoltaic panel systems shall be designed for the following load cases: (1) Dead Load (including photovoltaic panel weight) plus snow load in accordance with Table R301.2(1) (2) Dead Load (excluding photovoltaic panel weight) plus roof live load or snow load, whichever is greater, in accordance with Section R301.6. ... R324.7.1 Fire separation distances. Ground- mounted photovoltaic systems shall maintain a fire separation distance of 7 feet 0 inches from any other accessory or principle structure or as required by the McHenry County Unified Development Ordinance.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-5: Supplement contains: Local legislation current through Ord. A25-0037, passed 8-19-2025 | State legislation current through ALS 2025 Pamphlet No. 1).
Full Breakdown
McHenry County's Planning & Development Department reviews solar installations through Section 15.08.010's amendment to Section R324, Solar Energy Systems, part of the same 2021 IRC amendment package, Ordinance O-202211-10-052, effective January 1, 2023, that governs all residential construction permits. Photovoltaic systems must be 'designed and installed in accordance with the McHenry County Unified Development Ordinance...and NFPA 70,' and every inverter 'shall be listed and labeled in accordance with UL 1741'; systems tied to the grid must use inverters specifically listed for utility interaction. Solar thermal systems installed for water or space heating are separately routed to the Unified Development Ordinance and the International Fire Code rather than the photovoltaic provisions.
Structural review is not optional. R324.4.1 requires roof structures supporting photovoltaic panels to be engineered for two load cases: dead load including the panel weight plus snow load per Table R301.2(1), and dead load excluding panel weight plus roof live load or snow load, whichever governs, per Section R301.6. For ground-mounted arrays, R324.7.1 sets a fire separation distance of 7 feet 0 inches from any other accessory or principal structure on the lot, unless the Unified Development Ordinance requires more.
Because solar work is folded into the standard building permit rather than issued as its own category, the same Planning & Development plan review, County Board fee schedule, and inspection sequence used for other residential alterations applies to a photovoltaic installation.
Violations & Fines
Solar installations fall under the same IRC amendment package as the rest of residential construction, so an inverter that isn't UL 1741-listed, a roof not engineered for the added load, or a ground-mounted array closer than 7 feet to another structure is a violation of the amended code carrying the Section 15.08.020(B) minimum fine of $200 per offense, with each week uncorrected treated as a separate offense.
Frequently Asked Questions
Do I need a permit to install rooftop solar panels in unincorporated McHenry County?
What inverter standard does McHenry County require?
How far from my house does a ground-mounted solar array have to sit?
Does my roof need extra engineering to carry solar panels?
Sources & Official References
Other rules in McHenry County
Compare McHenry County to another location·View the Illinois solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.