Key Facts

Governing section
County LUDC Sec. 35.30.160
Planning permit
not required for roof or freestanding solar
Still required
Building, Electrical, Plumbing permits
Discretionary permit
Solar Use Permit, adverse-impact finding only
Appeal path
Planning Commission, Ch. 35.102
Permit condition
must mitigate impact at lowest feasible cost

Summary

Roof-mounted and freestanding solar energy systems in the unincorporated county skip design review and planning permits outright, but still need a Building, Electrical, and Plumbing permit, and, if the Building Official has a good-faith concern about a specific health or safety impact, a discretionary Solar Use Permit.

City-specific rules exist: Santa Maria has its own panel permits rules that differ from Santa Barbara County's county-level regulations. If you live in Santa Maria, check the city-specific page instead.

35.30.160 - Solar Energy Systems. Solar energy systems located on the roof of an existing structure and freestanding solar energy systems are exempt from design review and do not require planning permit approval, however such systems do require the issuance of a Building Permit, Electrical Permit, Plumbing Permit and/or Solar Use Permit, as applicable, in compliance with Chapter 10 (Building Regulations) of the County Code. A. Solar Use Permit. If the Building Official has a good faith belief that the solar energy system could have a specific, adverse impact upon the public health and safety, the Building Official may require the applicant to additionally apply for a Solar Use Permit in compliance with this Subsection. The decision of the Building Official to require the applicant to apply for a Solar Use Permit may be appealed to the Commission in compliance with Chapter 35.102 (Appeals).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 44 Update 1).

Full Breakdown

LUDC Sec. 160 exempts roof-mounted and freestanding solar energy systems from design review and from needing a planning permit, but they still must go through Chapter 10's Building Permit, Electrical Permit, and Plumbing Permit process like any other installation. 80's permit-filing rules. The Building Official cannot deny a Solar Use Permit unless written findings, based on substantial evidence, show a specific adverse impact with no feasible way to mitigate or avoid it; those findings must also explain why other, less restrictive options were rejected. To approve or conditionally approve a Solar Use Permit, the Building Official has to find that the installation will not have a specific adverse health or safety impact, that it conforms to the Development Code or fits a legal nonconforming exception, that it sits on a legally created lot, and that the property is current on zoning compliance and any zoning-violation fees.

Any conditions attached to a Solar Use Permit have to mitigate the specific impact at the lowest feasible cost. 102, and the permit itself stays valid only as long as the installation keeps complying with the Development Code and its own conditions.

Violations & Fines

A Solar Use Permit lapses the moment the installation falls out of compliance with the Development Code or its own conditions, per Sec. 35.30.160.A.4. Installing solar equipment without the required Building, Electrical, or Plumbing permit exposes the owner to the same additional penalty fee under Sec. 10-1.15 that applies to any other unpermitted construction in the unincorporated county.

Frequently Asked Questions

Do I need a planning permit to put solar panels on my roof in unincorporated Santa Barbara County?
No. Sec. 35.30.160 exempts roof-mounted and freestanding solar energy systems from design review and planning permit approval, though you still need the standard Building, Electrical, and Plumbing permits under Chapter 10 before installing.
When would the County require a Solar Use Permit for solar panels?
Only when the Building Official has a good-faith belief the installation could have a specific, adverse impact on public health or safety. The Building Official cannot deny the permit without written findings that no feasible mitigation exists.
Can I appeal if the County denies my Solar Use Permit?
Yes. Decisions on a Solar Use Permit under Sec. 35.30.160 can be appealed to the Planning Commission under Chapter 35.102, the same appeals chapter used for other Development Code permit decisions.
Does a Solar Use Permit stay valid forever once issued?
No. Under Sec. 35.30.160.A.4, the permit remains valid only as long as the installation keeps complying with all applicable Development Code provisions and the specific conditions attached to the permit.

Sources & Official References

Other rules in Santa Barbara County

All Santa Barbara County rules

California rules heatmap·Compare Santa Barbara County to another location·View the California solar energy overview

Get notified when Panel Permits in Santa Barbara County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Panel Permits in Cities Across Santa Barbara County