Key Facts

Applies to
New development in Cardinal Street IMA only
Requirement
Separate reclaimed water distribution system
Available water test
Source within 1,000 feet, or planned within 5 years
Fallback
Reserve pipeline route in road right-of-way
Related rule
Central water and sewer required, § 3426.F.1
Enforcing office
Growth Management, Land Development Division
Governing ordinance
Ord. 2026-A16, effective June 22, 2026

Summary

New development inside Citrus County's Cardinal Street Interim Master Area, the Cardinal Mixed Use (CMU) District along the Cardinal Street corridor, must install a separate reclaimed water distribution system under Land Development Code § 3426.F.3. The mandate applies only within this mapped overlay in unincorporated Citrus County, not countywide, and turns on whether a reclaimed water source sits within 1,000 feet.

These county ordinances apply to unincorporated areas of Citrus County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

3. Reclaimed Water. New development within the Cardinal Street IMA shall install a separate reclaimed water distribution system to promote beneficial reuse of available reclaimed water. Available reclaimed water means that a source of reclaimed water meeting the applicable regulatory requirements for public access, and with sufficient capacity to provide service to the development, is present within 1,000 feet of the development, or is in the planning and design stages and will meet those requirements within the subsequent five years. Where reclaimed water is not available, new development shall reserve a pipeline route within the roadway right-of-way to allow for future installation of a reclaimed water distribution system.

Full Breakdown

3 of the Citrus County Land Development Code, part of the Cardinal Mixed Use (CMU) District development standards adopted under Ordinance 2026-A16 (effective June 22, 2026), requires new development within the Cardinal Street Interim Master Area (IMA) to install a separate reclaimed water distribution system. The stated purpose is to promote beneficial reuse of available reclaimed water rather than relying only on potable water for irrigation and other non-drinking uses. The code defines 'available reclaimed water' precisely: a source meeting applicable regulatory requirements for public access, with enough capacity to serve the development, must sit within 1,000 feet of the site, or be in the planning and design stages with a five-year path to meeting those requirements.

3 instead requires the project to reserve a pipeline route within the roadway right-of-way so a reclaimed water main can be installed once service becomes available. 2. The Cardinal Street IMA covers a defined geographic area shown on the LDC's Figure 1 map, not the whole county, so property outside that overlay is not bound by this section. The rule has no effect inside the City of Crystal River or the City of Inverness, both of which administer their own municipal codes separate from Citrus County's Land Development Code.

The Growth Management Department's Land Development Division reviews site development plans and plats for compliance with Chapter Three utility standards, including this reclaimed water subsection, before approving new development in the IMA.

Violations & Fines

Section 3426.F.3 carries no separate fine schedule of its own; it functions as a site development plan and plat approval standard enforced by the Growth Management Department's Land Development Division. A project that omits the required reclaimed water distribution system, or fails to reserve the fallback pipeline route in the right-of-way, does not receive plan approval, which blocks the building permits and certificates of occupancy that depend on that approval.

Frequently Asked Questions

Does Citrus County require reclaimed water lines everywhere in the county?
No. The reclaimed water distribution system mandate in LDC § 3426.F.3 applies only to new development inside the Cardinal Street Interim Master Area, the Cardinal Mixed Use District along the Cardinal Street corridor. Property outside that mapped overlay, and property inside Crystal River or Inverness city limits, is not governed by this county Land Development Code section.
What counts as 'available' reclaimed water under this section?
The code defines available reclaimed water as a source meeting public-access regulatory requirements, with capacity to serve the project, located within 1,000 feet of the development, or a source in the planning and design stages that will meet those requirements within five years. Either condition triggers the connection requirement.
What happens if reclaimed water is not available near the site at all?
The developer is not exempted. Section 3426.F.3 requires the project to reserve a pipeline route within the roadway right-of-way so a reclaimed water distribution line can be installed once service becomes available, preserving the corridor for the county's future reuse infrastructure.
Who reviews compliance with the reclaimed water requirement?
The Citrus County Growth Management Department's Land Development Division reviews site development plans and plats for the Cardinal Street IMA against Chapter Three's utility standards, including § 3426.F.3, before approving the project; noncompliant plans are not approved.

Sources & Official References

Other rules in Citrus County

All Citrus County rules

Florida rules heatmap·Compare Citrus County to another location·View the Florida water use rules overview

Get notified when Recycled Water Rules in Citrus County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.