Lead Paint

When a tenant, resident or occupant complains about a possible lead hazard, Bakersfield must send an inspector out. Municipal Code § 8.27.012, added in 2026 under state Health and Safety Code § 17970.5, requires a mandatory inspection and a written plan for mitigating any hazard the inspector confirms.

Key details: Trigger: Complaint from tenant, resident, occupant, or agent. State law basis: Health & Safety Code § 17970.5. City duty: Mandatory inspection + mitigation plan. Enforcing office: Building director (§ 8.27.020). Added by: Ordinance 5216 § 1 (2026).

Section 8.27.012 itself imposes a duty on the city, not a fine schedule on property owners, so it doesn't carry its own penalty clause: unlike § 8.27.010, whose violations are expressly punishable under the general penalty in § 1.40.010. If an inspection confirms a lead hazard or substandard condition and the owner doesn't complete the mitigation actions the city specifies, the building director can instead pursue nuisance abatement under Chapter 8.80 as authorized by § 8.27.030, with costs recoverable from the property.

Electrical Permits

Bakersfield adopts the 2025 California Electrical Code by reference under Municipal Code § 15.11.010, making the state code the enforceable electrical standard citywide as modified by the building department's own chapter amendments.

Key details: Adopted code: California Electrical Code, 2025 Edition. Governing section: BMC § 15.11.010. Current ordinance: Ord. 5204 § 5, 2025. Enforcing department: Bakersfield Building Department. Local amendments: None beyond adoption in Ch. 15.11.

Electrical work performed without a permit, or not conforming to the adopted 2025 California Electrical Code, is enforced by the Bakersfield building department through correction notices and inspection holds; work that fails inspection must be corrected before the permit can be finaled and utility service connected.

Plumbing Permits

Bakersfield adopts the 2025 California Plumbing Code by reference under Municipal Code § 15.09.010, with the building department administering permits and inspections. Local amendments cover water heater floor support, slab plumbing, sewer connection distance and restroom facilities for small businesses.

Key details: Adopted code: California Plumbing Code, 2025 Edition. Governing section: BMC § 15.09.010. Appeals board: Deleted locally (CPC § 107.1). Sewer availability distance: 1,000 ft (200 ft for ≤4 units). Enforcing department: Bakersfield Building Department.

Work performed without a permit or contrary to the adopted California Plumbing Code as locally amended is enforced through the city's building department inspection process; unpermitted slab plumbing, missing water heater floor support, or septic hookups lacking the required Kern County LAMP permit can trigger correction orders and re-inspection before occupancy or final sign-off.

Building Inspections

Bakersfield's building code splits construction oversight into special inspections and structural observations: § 15.05.080 requires special inspection of concrete work above set thresholds, while § 15.05.090 makes owners hire a structural observer who must sign off before the building official accepts the work.

Key details: Special inspection standard: BMC § 15.05.080 (CBC § 1705.3). Structural observation standard: BMC § 15.05.090 (CBC § 1704.6). Concrete inspection exemption: f'c ≤ 2,500 psi, ≤3 stories. Preconstruction meeting: Required before observations start. Final sign-off: Deficiency-free report required for acceptance.

Proceeding to a later construction stage without the required special inspection or without the structural observer's stage report is a violation of Title 15, enforceable under the general penalty in § 1.40.010 (up to $250 per repeat infraction, or a misdemeanor up to $1,000/six months), and the building official can withhold acceptance of the work under § 15.05.090 until a final deficiency-free report is filed.

Building Permits

Bakersfield's buildings and construction code, adopted at § 15.04.050, reaches new building construction and any new mechanical, plumbing, electrical or sign system; leave a permitted project stalled 180 days and § 15.04.110 forces you to re-permit within 30 days or demolish within 60.

Key details: Applicability standard: BMC § 15.04.050. Adoption/scope of permitting: BMC § 15.05.010 (2025 CBC). Suspension trigger: 180+ days of inactivity. New permit deadline: 30 days from director's notice. Demolition deadline: 60 days from director's notice.

Building without a required permit, or letting a permitted project sit stalled past the notice deadlines in § 15.04.110, is a Title 15 violation punishable under the general penalty at § 1.40.010: up to $250 for a repeat infraction or a misdemeanor carrying up to $1,000 or six months in county jail, with each day of continued noncompliance a separate offense.

Carbon Monoxide Detectors

Every Bakersfield short-term rental must have working carbon monoxide detectors, smoke detectors, and fire extinguishers under Section 17.74.060(C), maintained in compliance with life, fire, and safety codes. The same provision requires posted emergency exit route information and emergency contact details, and the equipment mandate is enforceable through the chapter's citation and permit-renewal system.

Key details: Required equipment: CO detector, smoke detector, fire extinguisher. Standard: Working & maintained per life/fire/safety codes. Posted info required: Exit routes, extinguisher locations, contacts. Enforcement: Citation counts toward 2-strike renewal bar.

Operating a Bakersfield STR without a working carbon monoxide detector, smoke detector, or fire extinguisher breaches Section 17.74.060(C) and can be cited as a public-safety hazard under Section 17.74.070(A)(7). The citation counts toward the two-citation cap in Section 17.74.040(D) that bars permit renewal, and enforcement proceeds under Chapter 1.40 alongside Title 8, 9, 15, and 17 code enforcement procedures per Section 17.74.070(G).

Green Building Code

Bakersfield enforces California Green Building Standards Code Title 24 Part 11 known as CALGreen. New construction must meet baseline mandatory measures for energy, water, indoor air quality, and construction-waste recycling, plus voluntary tier elevations.

Key details: State code: Title 24 Part 11 CALGreen. Water savings: 20 percent indoor reduction. Waste diversion: Sixty-five percent minimum. EV-ready: Required for new garages.

Failing to meet CALGreen mandatory measures during construction can block certificate of occupancy, trigger corrective work orders, and result in administrative fines starting at 250 dollars per violation.

The Bottom Line

Bakersfield's building safety rules are a mixed bag. Some areas are strict, others are relaxed, and the details matter. The best approach is to check the specific rule that applies to your situation rather than assuming Bakersfield is broadly strict or permissive.