Every city handles environmental rules a little differently. In Rockville, Maryland, there are 4 distinct rules that residents and property owners should be aware of. Some are stricter than what neighboring cities enforce, and others are more relaxed. Here is what you need to know.

Flood Zones

Any filling, grading, new construction, or substantial improvement inside a FEMA-mapped special flood hazard area in Rockville needs both a City floodplain variance and a floodplain permit before work starts.

Key details: Requires: Floodplain variance + permit. Administered by: Dept. of Public Works. NFIP participation since: January 5, 1978. Permit-only exemptions: Split-rail fences, minor landscaping. Max fine: $1,000/violation/day.

Starting development in a special flood hazard area without an approved floodplain variance and permit violates Sec. 10-46 and can draw a stop-work order, abatement order, and administrative fines up to $1,000 per violation per day under Sec. 10-47.

This is one of the stricter rules in Rockville's municipal code. If you are unsure whether your situation complies, it is worth checking with the city before proceeding.

Flood Elevation Requirements

New and substantially improved residential structures in Rockville's flood hazard areas must have their lowest floor at least two feet above the base flood elevation: the City's mandatory freeboard.

Key details: Residential freeboard: 2 ft above base flood elev.. Critical facilities freeboard: 1 ft (Sec. 10-75). Electric panelboard: 3 ft above BFE, Sec. 10-73(6). Verified by: Licensed surveyor elevation cert..

Building below the required flood protection elevation without an approved floodplain variance violates Sec. 10-46 and Sec. 10-78, exposing the project to a stop-work order and administrative fines up to $1,000 per violation per day under Sec. 10-47.

Stormwater Management

Any Rockville project disturbing 5,000+ square feet, or adding as little as 250 square feet of new pavement on non-residential land, must provide on-site stormwater management.

Key details: Disturbance threshold: 5,000 sq ft or more. Residential threshold: 2,000 sq ft new impervious. Other property threshold: 250 sq ft new impervious. Permit: Required before system installation. Standard: MDE Stormwater Design Manual.

Disturbing land or adding impervious area above the SWM thresholds without an approved SWM concept, construction plan and permit is prohibited; installing a stormwater system before permit issuance is a separate, standalone violation.

Erosion Control

Rockville requires an approved sediment control plan and permit before any land-disturbing construction of 5,000 or more square feet, 100 or more cubic yards of grading, or any new single-family, townhouse or semi-detached home, enforced by the Department of Public Works.

Key details: Trigger: 5,000+ sq ft disturbed area. Or: 100+ cubic yards of grading. Always covered: new single-family/townhouse homes. Enforced by: Dept. of Public Works.

Land disturbance without an approved plan and permit is barred outright under Β§ 19-101(a); unpermitted violations default to a municipal infraction under City Code Β§ 1-9, fined up to $400 per day.

The Bottom Line