If you live in Daytona Beach or are thinking about moving there, hurricane preparedness are one of those things you probably won't think about until they affect you directly. Daytona Beach has 2 specific rules on the books covering different aspects of hurricane preparedness, and some of them might surprise you.

Storm Debris

During a declared state of emergency, Daytona Beach may enter private streets and rights-of-way inside any subdivision to collect storm debris blocking a right-of-way or utility easement, but only after the street's owner signs a written agreement holding the county, state and federal government harmless. City Code Β§ 2-3(b)(11) supplies the authority.

Key details: Trigger: Proclaimed state of emergency. Authority: City may enter private ROW for debris. Condition: Owner must sign hold-harmless agreement. Adopted: Ord. 06-397 (2006), amended Ord. 11-221 (2011). Statute basis: Fla. Stat. ch. 252 CEMP.

Section 2-3 sets no fine of its own; it grants emergency authority to the city rather than imposing a duty on residents. The practical consequence for a subdivision with private streets is that if the street's owner will not sign the hold-harmless release, city debris crews cannot legally enter, leaving debris removal to the association's own contractor at the association's expense.

Flood Elevation

Every new structure in Daytona Beach must set its finished floor at least 12 inches above the crown of the adjacent road, a citywide standard under LDC Section 6.23 that applies on top of, and yields to, any stricter Florida Building Code flood elevation requirement.

Key details: Minimum elevation: 12 inches above road crown. Survey deadline: 20 days after slab poured. Enforcement tool: Building official's Stop Work Order. Adopted by: Ord. No. 16-203 (2016), amended 2022.

Missing the 20-day deadline to file the as-built finished-floor survey after the slab is poured triggers a Stop Work Order from the building official, stopping all further construction until an accurate survey is on file. Building below the required 12-inch elevation without engineering division approval is a Land Development Code violation subject to Article 10's civil citations and correction orders.

The Bottom Line

Daytona Beach's hurricane preparedness rules are a mixed bag. Some areas are strict, others are relaxed, and the details matter. The best approach is to check the specific rule that applies to your situation rather than assuming Daytona Beach is broadly strict or permissive.

These rules come from Daytona Beach's publicly available municipal code. For complete penalty schedules, exemption details, and answers to common questions, see the individual ordinance pages throughout this guide.