Bartholomew County, IN Building Safety: Building Permits (2026)
Key Facts
- Permit trigger
- Required once cost exceeds $300 (§150.36)
- Scope
- Unincorporated county only; fences excluded (§150.04)
- Application needs
- Fee, plans, plot plan for new structures (§150.35)
- Permit term
- Good 2 years, void after 6 months unused (§150.40)
- Renewal fee
- 50% of original permit fee (§150.20(R))
- Unpermitted work penalty
- Min $5, doubles permit cost (§150.38)
Summary
A building permit is required in unincorporated Bartholomew County before any construction, alteration or repair whose cost exceeds $300, under section 150.36 of the county Building Code. Section 150.35 requires the application to include the applicable fee, plans and specifications, and a plot plan for new construction. Section 150.04 limits the chapter to the unincorporated area and excludes fences and mobile structures certified under I.C. 22-15-4.
§ 150.35 PERMIT APPLICATION. ... (A) All pertinent forms shall be provided by the Department. No permit shall be issued for construction unless the application for the permit is accompanied by: (1) The payment of appropriate fees as described herein; (2) Plans and specifications showing the construction to be accomplished; and (3) In the event of construction of a new structure, or extension to an existing structure, a plot plan showing the location of the new structure or the extension to existing structure, as well as all other existing improvements and lot boundaries. ... § 150.36 PERMIT REQUIRED. A permit shall be obtained before beginning construction, alteration or repair of any building or structure, the cost of which exceeds $300, using forms furnished by the Chief Code Enforcement Officer, and all fees required by this Code shall be paid to the office of Department of Code Enforcement.
Full Breakdown
C. 22-15-4. 36 sets the trigger for a permit: any construction, alteration or repair costing more than $300 requires one before work begins, using forms furnished by the Chief Code Enforcement Officer, with fees paid to the Department of Code Enforcement. C. 22-15-3-1 must also be provided before the permit issues. 21, ranging from a $200 minimum for a one- and two-family dwelling to a $400 minimum, capped at $10,000, for new commercial, industrial or multi-family construction. 20(R).
Violations & Fines
Beginning construction before obtaining the required permit draws the section 150.38 penalty: a minimum $5 fee, and generally double the cost of the permit that should have been obtained. Continuing to build, occupy or use a structure contrary to the Building Code is a violation under section 150.46, punishable under section 150.99 by a fine of $100 to $500, with each day of the violation a separate Class C infraction.
Frequently Asked Questions
When do I need a building permit in unincorporated Bartholomew County?
What has to go with a building permit application?
Does the county Building Code cover fences?
What happens if I build without a permit first?
Sources & Official References
Other rules in Bartholomew County
Compare Bartholomew County to another location·View the Indiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.