Key Facts

Adopted building code
IBC 2018, § 18-1
Adopted residential code
IRC 2018, Ch. 1-11 + App. E,F,Q,S
Ordinance
No. 21-22, adopted 5-17-2022
Effective date
July 1, 2022
Pre-adoption applications
Governed by prior Chapter 18

Summary

Calvert County adopted the 2018 International Building Code and most of the 2018 International Residential Code, with local amendments, as its building code effective July 1, 2022. Building permit applications filed before that date stay under the prior chapter; anything filed after must meet the new code.

These county ordinances apply to unincorporated areas of Calvert County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 18-1. Codes adopted by reference; amendments and deletions. A. The International Building Code 2018 (IBC) published by the International Codes Council, Inc., is hereby adopted as the Building Code for Calvert County, with the insertions, additions, deletions, and changes to the IBC set forth in Exhibit A ... hereto. ... § 18-2. Filing; effect on prior building permit applications. This chapter shall take effect July 1, 2022, upon execution and filing with the Clerk of the Circuit Court; provided, however, that any building permit that was applied for prior to the adoption of this chapter shall be subject to the provisions of Chapter 18 of the Code of Calvert County in effect prior to the adoption of this chapter. Any building permit applied for after the effect date of this chapter is subject to this chapter.

Full Breakdown

Chapter 18 of the Code of Calvert County, Building Construction, was adopted by the Board of County Commissioners on May 17, 2022 by Ordinance No. 21-22, replacing an earlier version of the chapter dating to 1996 and amended in 2011. Section 18-1 adopts the International Building Code 2018 (IBC), published by the International Code Council, as the Building Code for Calvert County, along with the insertions, additions, deletions and changes to the IBC that the county wrote into an Exhibit A attached to the ordinance.

The same section adopts Chapters 1 through 11 and Appendixes E, F, Q and S of the International Residential Code 2018 (IRC) for buildings covered by that code, again subject to Exhibit A's local insertions, omissions and changes. Because the IBC and IRC set out the actual triggers, exceptions and procedures for when a building permit is required, in Calvert County outside Chesapeake Beach and North Beach those adopted 2018 editions, as locally amended, are the operative permitting rules administered by the county's Inspections and Permits function; Chapter 18 itself does not restate those permit triggers, it adopts them by reference.

Section 18-2 fixes the transition: the chapter took effect July 1, 2022 upon filing with the Clerk of the Circuit Court, and any building permit application filed before that adoption is instead handled under the version of Chapter 18 that was in effect before the 2022 ordinance, while any application filed after the effective date is governed by the 2022 chapter and its adopted 2018 codes.

Violations & Fines

Chapter 18 itself does not print a separate penalty schedule for building without a permit; that enforcement runs through the adopted International Building Code and International Residential Code 2018 editions and the county's Inspections and Permits process, which can require compliance before work proceeds or occupancy is granted.

Frequently Asked Questions

What building code does Calvert County use?
Section 18-1 adopts the 2018 International Building Code and most of the 2018 International Residential Code, both with county-specific amendments in Exhibit A, as the Building Code for Calvert County outside Chesapeake Beach and North Beach.
When did the current building code take effect?
Chapter 18 took effect July 1, 2022, once filed with the Clerk of the Circuit Court, under Ordinance No. 21-22 adopted May 17, 2022, per § 18-2.
Which rules apply to a permit I applied for before the 2022 update?
Section 18-2 keeps any building permit applied for before the 2022 ordinance's adoption under the prior version of Chapter 18 that was in effect at that time, rather than the current 2018 IBC/IRC edition.
Does Chapter 18 list exactly when a permit is required?
No. Chapter 18 adopts the IBC and IRC 2018 editions by reference as the county's building code; the specific permit triggers and exceptions live in those adopted codes and Exhibit A's local amendments, not printed as separate county text.

Sources & Official References

Other rules in Calvert County

All Calvert County rules

Compare Calvert County to another location·View the Maryland building safety overview

Get notified when Building Permits in Calvert County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.