Campbell County, KY Building Safety: Building Permits (2026)
Key Facts
- Permit issuer
- County zoning office
- Application validity
- 90 days, one 60-day extension
- Construction window
- 12 months from foundation start
- Construction extension
- 6 months with proof of cause
- Pre-chapter permits valid
- 730 consecutive calendar days
- Enforcement agency
- Campbell Co. Dept. of Planning & Zoning
- Penalty
- Class B misdemeanor, per day (§154.999)
Summary
In unincorporated Campbell County, no building or structure may be erected, moved, added to, or structurally altered without a permit from the zoning office. Applications require a completed form, an approved zoning permit, the required fee, and construction plans. A building permit application lapses after 90 days unless the Building Inspector grants a 60-day extension.
(A) Building permits required. No public or private building or other structure shall be erected, moved, added to, or structurally altered without a permit issued by the zoning office. No building permit shall be issued except in conformity with the provisions of this chapter, except after written order from the Board of Adjustments. ... (B)(6) All building permit applications shall be good for only 90 days after which time they shall expire and no building permit may be issued, except an extension of not more than 60 days may be permitted by the Building Inspector. ... If after the work described in the building permit has been started, the building permit shall expire after a period of 12 months, providing that a six-month extension may be permitted if sufficient proof can be demonstrated why the work described in the building permit was not completed as herein specified.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-50: Supplement contains: Local legislation current through Ord. O-09-2026, passed 8-5-26; and Res. R-42-26, passed 7-15-26; and State legislation current through KRS Pamphlet 2025).
Full Breakdown
277 sets the building permit rule for the unincorporated county: no public or private building or other structure can be erected, moved, added to, or structurally altered without a permit issued by the zoning office, and no permit issues except in conformity with the zoning chapter unless the Board of Adjustments has ordered otherwise in writing. 279 fee, a development plan when required, and duplicate plans sufficient to show compliance with the building code and Kentucky Revised Statutes. The zoning office either approves the plans or returns them marked "Disapproved" with the reasons stated and the reviewer's signature attached; approved applicants receive the building permit while the office keeps a duplicate.
Applications are only good for 90 days, after which they expire and cannot be issued unless the Building Inspector grants a one-time extension of up to 60 days. Once work has started, treated as begun when the foundation is complete, the permit itself expires 12 months later, though a six-month extension is available on sufficient proof the delay was justified. Permits issued under the county's prior building code before this chapter's adoption stay valid for 730 consecutive calendar days from issuance; if construction has not started by then the permit voids and a new one is required.
No building or occupancy permit may issue, and no one may build, alter, or occupy a structure, unless a zoning permit has already been approved under this chapter. Chapter 150 separately adopts the Kentucky Building Code and Kentucky Residential Code by reference, with the Campbell County Department of Planning and Zoning designated as the local enforcement agent and all inspections performed by state-certified inspectors.
Violations & Fines
Building without the required permit, or building at variance with the approved plans, is a violation of Chapter 154 punishable under § 154.999 as a class B misdemeanor, with each day of the violation counted as a separate offense. The zoning office may also disapprove or void permit applications that misrepresent required information, and no certificate of occupancy or building permit may be issued for work lacking an approved zoning permit.
Frequently Asked Questions
Do I need a permit to add onto my house in unincorporated Campbell County?
How long is a building permit application good for?
What happens if I don't finish construction after my permit is issued?
Who inspects buildings and enforces the permit rules in Campbell County?
Sources & Official References
Other rules in Campbell County
Compare Campbell County to another location·View the Kentucky building safety overview