Key Facts

Governing code
Minnesota State Building Code, adopted by reference
Applies to
Unincorporated Carver County only
Administering department
Land Management Department
Enforcing official
Minnesota Certified Building Official
Unpermitted work started
Investigation fee added to permit fee
Refund cap
Up to 80% within 180 days, no work done
Violation class
Misdemeanor, each day a separate offense

Summary

Carver County requires a building permit for work governed by the Minnesota State Building Code, which the county has adopted wholesale for the unincorporated area. The Land Management Department administers the code through a Minnesota Certified Building Official, and starting work before a permit issues triggers an extra investigation fee.

These county ordinances apply to unincorporated areas of Carver County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 150.01 STATE BUILDING CODE ADOPTED. The currently enforced Minnesota State Building Code (Residential and Commercial), established pursuant to M.S. §§ 326B.101 to 326B.197, as amended from time to time, is hereby adopted as the building code (hereinafter “code”) for the county. The Minnesota State Building Code is hereby incorporated in this subchapter as if fully set out herein.

§ 150.02 APPLICATION, ADMINISTRATION, AND ENFORCEMENT. This code shall be effect in the unincorporated areas of the county. The Land Management Department shall be the Building Code Department of the county. This code shall be enforced by a Minnesota Certified Building Official designated by the county to administer the code.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-20: Supplement contains: Local legislation current through Ord. 111-2025, passed 7-25-25).

Full Breakdown

02, that code applies only "in the unincorporated areas of the county": incorporated cities inside Carver County run their own building departments, so this permit regime never reaches property inside a city. The Land Management Department is designated the county's Building Code Department, and enforcement runs through a Minnesota Certified Building Official appointed by the county, not a generalist code enforcement officer. 03(A) by the county's adopted fee schedule and the State Building Code, plus a surcharge fee collected on every permit issued for work the code governs.

03(B) is the operative "when required" trigger in practice: if work governed by the code has already started before a permit is obtained, the county collects an investigation fee on top of the normal permit fee, and paying it does not excuse the applicant from the code's other requirements or from any other penalty. 03(C) the Building Official may refund up to 80% of a paid permit fee when no work has been done, but only on a written application the original permittee files within 180 days of paying, and plan review fees are never refundable regardless of whether the project proceeds.

Violations & Fines

Violating any provision of the building code, or filing a false statement in a required document, is a misdemeanor under § 150.04(A), with each day the violation continues charged as a separate offense. Starting work without a permit does not avoid enforcement; § 150.03(B) layers an investigation fee on top of the permit fee for unpermitted work already begun. Section 150.04(B) also lets the county pursue injunctive relief and other court remedies to prevent, restrain, correct, or abate a violation or a threatened one.

Frequently Asked Questions

Does Carver County have its own building code?
No. Section 150.01 adopts the Minnesota State Building Code (Residential and Commercial) under M.S. §§ 326B.101 to 326B.197 outright and incorporates it into the county code "as if fully set out herein," so state code triggers, not a separate county list, control when a permit is required.
Who reviews and issues building permits in Carver County?
The Land Management Department, acting as the county's Building Code Department under § 150.02, administers the process, and enforcement is carried out by a Minnesota Certified Building Official designated by the county.
What happens if I start construction before getting a permit?
Section 150.03(B) requires the county to collect an investigation fee in addition to the normal permit fee whenever work requiring a permit has already begun, and paying that fee does not excuse compliance with the rest of the code or exempt you from other penalties.
Can I get my permit fee back if I cancel the project?
Only partially. Under § 150.03(C) the Building Official may refund up to 80% of the permit fee if no work has been done, but you must file a written request within 180 days of paying, and plan review fees are never refunded.

Sources & Official References

Other rules in Carver County

All Carver County rules

Compare Carver County to another location·View the Minnesota building safety overview

Get notified when Building Permits in Carver County, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.