Dixmont, ME Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Permit issuer
Dixmont Code Enforcement Officer
Decision deadline
15 days after a completed application
Exempt from ordinance
Accessory structures under 80 sq. ft.
No-cost permit
Accessory structures 80 to 199 sq. ft.
After-the-fact permit
Twice the timely fee plus enforcement costs
Denial appeal
Board of Appeals within 30 days

Summary

Dixmont requires a permit from the Code Enforcement Officer before any building, accessory structure, enlargement or mobile home siting begins. The officer returns the approved permit or a written denial within 15 days of a completed application. Accessory structures under 80 square feet are outside the ordinance, and those from 80 to 199 square feet need a no-cost permit.

A. Before the construction of any building, accessory structure, enlargement of buildings, or accessory structures, or siting of a mobile home shall begin, the owner or authorized agent for the owner shall submit to the Code Enforcement Officer an application for a permit for such proposed work and the appropriate application fee in accordance with Section 7 of the Ordinance. ... C. The Code Enforcement Officer shall review all completed applications for compliance with the standards contained in this Ordinance. Within 15 days of receipt of the completed application, the Code Enforcement Officer shall either return the approved permit to the applicant or transmit to the applicant written notice of denial. ... The party aggrieved by the denial of a permit may appeal that decision to the Dixmont Board of Appeals within 30 days in accordance with Section 12 of this Ordinance.

Full Breakdown

The Town of Dixmont Building Code Ordinance, dated March 21, 2009 and officially amended March 17, 2018, sets the permit trigger in Section 6(A). Before the construction of any building, accessory structure, enlargement of buildings or accessory structures, or siting of a mobile home begins, the owner or authorized agent submits an application and the application fee to the Code Enforcement Officer, on a form the officer supplies. Section 2 applies the permit procedure to the construction, placement, relocation, enlargement and replacement of all buildings and accessory structures in Dixmont. For any building that needs a subsurface wastewater disposal system, Section 6(B) bars a complete application until it includes the Maine site evaluation form HHE-200, completed by a licensed site evaluator and showing adequate soil conditions.

Under Section 6(C) the officer reviews completed applications against the ordinance standards and, within 15 days of receipt, either returns the approved permit or sends written notice of denial citing the specific respects in which the proposal does not comply. An aggrieved applicant appeals to the Dixmont Board of Appeals within 30 days under Section 12. Section 8 adds that no permit is issued unless the proposal complies with all applicable state law and regulation, local ordinances, and the listed standards, including a twenty (20) foot boundary line setback and a two (2) acre minimum lot.

Section 7(A) sets non-returnable application fees on a schedule by building type and size, and it exempts small accessory structures: those under 80 square feet, agricultural buildings included, are not subject to the ordinance, and those from 80 to 199 square feet need a no-cost permit. Section 7(B) covers after-the-fact permits: an application filed after substantial construction without the required permit must be accompanied or preceded by payment of twice the fee for a timely permit, plus enforcement costs set by the Code Enforcement Officer. Substantial construction includes pouring a slab or footings, installing piles, or any work beyond excavation; clearing, grading and filling do not count.

Violations & Fines

Building without the required permit is a violation handled by the Code Enforcement Officer. Section 7(B) requires an after-the-fact applicant to pay twice the timely fee plus enforcement costs, and the town keeps its right to enforce under Section 11. Violations are deemed a nuisance, the officer orders correction in writing, the selectmen are directed to bring legal action including injunctions and fines, and anyone who orders or conducts the work is penalized under 30-A M.R.S. § 4452.

Frequently Asked Questions

Do I need a permit to build a house or garage in Dixmont?
Yes. Section 6(A) requires the owner or authorized agent to apply to the Code Enforcement Officer before construction of any building, accessory structure, enlargement, or siting of a mobile home begins, and to pay the application fee under Section 7. The officer has 15 days from a completed application to return the permit or a written denial.
What happens if I already built without a permit?
Section 7(B) provides an after-the-fact permit, but the application must be accompanied or preceded by payment in full of twice the fee for a timely permit plus any enforcement costs the Code Enforcement Officer sets. Applying late does not limit the town's enforcement under Section 11, which covers written orders, legal action and penalties under 30-A M.R.S. § 4452.
What if my permit is denied?
The denial notice must cite the specific respects in which the proposal does not comply with state law, the ordinance or other Dixmont ordinances. You can appeal to the Dixmont Board of Appeals within 30 days under Section 12, which schedules a hearing within 14 days of receiving the request. Further appeals go to Penobscot County Superior Court under Rule 80B.

Sources & Official References

Other rules in Dixmont

All Dixmont rules

Compare Dixmont to another location·View the Maine building safety overview

Get notified when Building Permits in Dixmont, ME changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.