Dixmont, ME Building Safety: Building Permits (2026)
Key Facts
- Permit issuer
- Dixmont Code Enforcement Officer
- Decision deadline
- 15 days after a completed application
- Exempt from ordinance
- Accessory structures under 80 sq. ft.
- No-cost permit
- Accessory structures 80 to 199 sq. ft.
- After-the-fact permit
- Twice the timely fee plus enforcement costs
- Denial appeal
- Board of Appeals within 30 days
Summary
Dixmont requires a permit from the Code Enforcement Officer before any building, accessory structure, enlargement or mobile home siting begins. The officer returns the approved permit or a written denial within 15 days of a completed application. Accessory structures under 80 square feet are outside the ordinance, and those from 80 to 199 square feet need a no-cost permit.
A. Before the construction of any building, accessory structure, enlargement of buildings, or accessory structures, or siting of a mobile home shall begin, the owner or authorized agent for the owner shall submit to the Code Enforcement Officer an application for a permit for such proposed work and the appropriate application fee in accordance with Section 7 of the Ordinance. ... C. The Code Enforcement Officer shall review all completed applications for compliance with the standards contained in this Ordinance. Within 15 days of receipt of the completed application, the Code Enforcement Officer shall either return the approved permit to the applicant or transmit to the applicant written notice of denial. ... The party aggrieved by the denial of a permit may appeal that decision to the Dixmont Board of Appeals within 30 days in accordance with Section 12 of this Ordinance.
Full Breakdown
The Town of Dixmont Building Code Ordinance, dated March 21, 2009 and officially amended March 17, 2018, sets the permit trigger in Section 6(A). Before the construction of any building, accessory structure, enlargement of buildings or accessory structures, or siting of a mobile home begins, the owner or authorized agent submits an application and the application fee to the Code Enforcement Officer, on a form the officer supplies. Section 2 applies the permit procedure to the construction, placement, relocation, enlargement and replacement of all buildings and accessory structures in Dixmont. For any building that needs a subsurface wastewater disposal system, Section 6(B) bars a complete application until it includes the Maine site evaluation form HHE-200, completed by a licensed site evaluator and showing adequate soil conditions.
Under Section 6(C) the officer reviews completed applications against the ordinance standards and, within 15 days of receipt, either returns the approved permit or sends written notice of denial citing the specific respects in which the proposal does not comply. An aggrieved applicant appeals to the Dixmont Board of Appeals within 30 days under Section 12. Section 8 adds that no permit is issued unless the proposal complies with all applicable state law and regulation, local ordinances, and the listed standards, including a twenty (20) foot boundary line setback and a two (2) acre minimum lot.
Section 7(A) sets non-returnable application fees on a schedule by building type and size, and it exempts small accessory structures: those under 80 square feet, agricultural buildings included, are not subject to the ordinance, and those from 80 to 199 square feet need a no-cost permit. Section 7(B) covers after-the-fact permits: an application filed after substantial construction without the required permit must be accompanied or preceded by payment of twice the fee for a timely permit, plus enforcement costs set by the Code Enforcement Officer. Substantial construction includes pouring a slab or footings, installing piles, or any work beyond excavation; clearing, grading and filling do not count.
Violations & Fines
Building without the required permit is a violation handled by the Code Enforcement Officer. Section 7(B) requires an after-the-fact applicant to pay twice the timely fee plus enforcement costs, and the town keeps its right to enforce under Section 11. Violations are deemed a nuisance, the officer orders correction in writing, the selectmen are directed to bring legal action including injunctions and fines, and anyone who orders or conducts the work is penalized under 30-A M.R.S. § 4452.
Frequently Asked Questions
Do I need a permit to build a house or garage in Dixmont?
What happens if I already built without a permit?
What if my permit is denied?
Sources & Official References
Other rules in Dixmont
Compare Dixmont to another location·View the Maine building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.