Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permitting authority
Johnson County Zoning Administrator
Adopted codes
2021 IBC and IRC, as amended
Work-without-permit fee
equals the permit fee
Plan review fee threshold
construction valued over $15,000
First-offense infraction penalty
up to $750

Summary

Anyone building, altering, moving, enlarging, repairing or demolishing a building or structure in unincorporated Johnson County needs a building permit from the Zoning Administrator first, under UDO Section 8:1.27(A)(1). The same permit covers excavation, occupancy changes, and electrical, gas, mechanical or plumbing system work, with a short list of minor exemptions.

City-specific rules exist: Iowa City has its own building permits rules that differ from Johnson County's county-level regulations. If you live in Iowa City, check the city-specific page instead.

A. Permit Types and Application of Regulations. The following permit(s) shall be obtained from the Zoning Administrator in writing before starting or proceeding with any of the work described herein: 1. Building Permit. A building permit is required before starting or proceeding with any of the following: The construction, alteration, movement, enlargement, replacement, repair, equipment, or location, of any building or structure, or as otherwise required by Chapter 8:6 of this ordinance. Excavating for any building or structure. The removal or demolition of any building or structure, or part thereof which would require a building permit to construct. Changing the use or occupancy of any building or structure from one classification to another. The erection, installation, enlargement, alteration, repair, removal, conversion, or replacement of any electrical, gas, mechanical, or plumbing system.

Full Breakdown

27(A) of the Unified Development Ordinance requires anyone starting construction, alteration, movement, enlargement, replacement, repair or demolition of a building or structure in unincorporated Johnson County to obtain a building permit from the Zoning Administrator in writing before work begins. The same permit type covers excavation for a building or structure, a change in use or occupancy classification, and the erection, installation, alteration, removal, conversion or replacement of any electrical, gas, mechanical or plumbing system, all cross-referenced to Chapter 8:6, the Johnson County Building Code, which adopts the 2021 International Building and Residential Codes as amended.

2 excuses work such as detached accessory sheds of 200 square feet or less, fences under seven feet, retaining walls under four feet, and finish work like painting or carpeting, but exemption from a permit never excuses the underlying work from complying with the code. A permit is still required even where a structure is being rebuilt after fire, wind, flood or age-related damage. Permit fees are set by resolution of the Board of Supervisors and are based on the Building Official's valuation of the total construction work; projects valued over $15,000 also owe a separate plan review fee before the permit issues.

Anyone who starts work before obtaining the required permit owes a fee equal to the permit fee that would otherwise apply, collected whether or not a permit is ultimately issued, and paying that fee does not excuse compliance with the rest of the code. Building permits and certificates of occupancy remain revocable for as long as the project is out of compliance, and an appeal of a Building Official decision goes to the Board of Appeals for a fee set by the Board of Supervisors.

Violations & Fines

Starting work without the required permit triggers a fee equal to the permit fee that would have applied, on top of any permit eventually issued, under Section 109.4/R108.4. Because Chapter 8:6 sits inside Chapter 8 of the UDO, an uncorrected permit violation can also become a County infraction under Section 8:8.3, punishable by up to $750 for a first offense and $1,000 for a repeat violation, with permits and certificates of occupancy subject to revocation.

Frequently Asked Questions

When do I need a building permit in Johnson County?
A permit is required before you construct, alter, move, enlarge, replace, repair or demolish a building or structure, excavate for one, change its use or occupancy classification, or install, alter or replace an electrical, gas, mechanical or plumbing system, per UDO Section 8:1.27(A)(1).
What construction is exempt from a building permit?
The amended Section 105.2/R105.2 exempts limited work such as one-story accessory sheds of 200 square feet or less, fences under seven feet, retaining walls under four feet, above-ground pools under 5,000 gallons, and cosmetic finish work, but exemption from a permit does not excuse compliance with the rest of the code.
What if I start construction before getting a permit?
Section 109.4/R108.4 charges a fee equal to the amount of the permit that should have been obtained, collected whether or not a permit is later issued, and the Building Official can waive it only where an emergency required the work without one.
Who sets building permit fees in Johnson County?
Permit fees, plan review fees, and re-inspection fees are set by resolution of the Board of Supervisors, based on the Building Official's valuation of the total construction work, with a separate plan review fee due once a project's value exceeds $15,000.

Sources & Official References

Other rules in Johnson County

All Johnson County rules

Compare Johnson County to another location·View the Iowa building safety overview

Get notified when Building Permits in Johnson County, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.