Key Facts

Permit required for
Construction, alteration, demolition, occupancy change
Issuing office
York County Building and Codes Division
Zoning review
Required under §150.23 before issuance
Permit expiration
180 days without start/inspection
First-violation fine
Up to $200 civil fine
Escalated fine
Up to $2,000 after uncorrected 2nd violation

Summary

York County requires a building permit before anyone constructs, enlarges, alters, repairs, moves, demolishes or changes the occupancy of a building or structure in the unincorporated county, under § 150.20. Section 150.26 makes clear the permit only authorizes the specific work approved and does not excuse violations, and the county can still require corrections to plans or construction after the permit issues.

City-specific rules exist: Rock Hill has its own building permits rules that differ from York County's county-level regulations. If you live in Rock Hill, check the city-specific page instead.

§ 150.20 PERMITS REQUIRED. Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace and electrical, gas, mechanical, or plumbing system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the building and codes division and obtain the required permit.

§ 150.26 ISSUANCE OF PERMIT; SCOPE; REVOCATION; EXPIRATION; TERMINATION OF WORK.

(A) The building and codes division shall act upon an application for a permit without unreasonable or unnecessary delay.

(B) A permit issued shall be construed to be an authorization to proceed with the work and shall not be construed as authority to violate, conceal, alter or set aside any of the provisions of this chapter, nor shall the issuance of a permit prevent the department from thereafter requiring correction of errors in plans or in construction or of violations of this chapter.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-49: Supplement contains: Local legislation current through Ord. 3925, passed 6-16-25).

Full Breakdown

20 of the York County Code requires any owner or the owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system regulated by the code, to first apply to the Building and Codes Division and obtain a permit before work begins. 22 for anything where material quality affects code compliance. 24 bars issuing any permit for work in a floodplain area until Chapter 151's flood-management conditions are met.

01, and commercial plan reviews charged at 50% of the building permit fee. 26 treats the permit only as authorization to proceed with the approved work, not as permission to violate, conceal or set aside any code provision, and the division can still order corrections to plans or construction after issuance. A permit becomes invalid if work is not started and initially inspected within 180 days, or is abandoned for 180 days after starting, subject to written 180-day extensions the building official may grant for cause, and the official may revoke a permit issued on false or incomplete information, with no fee refund in that case.

Violations & Fines

Starting regulated construction, alteration, demolition or system work without the § 150.20 permit is punishable under § 150.99 by a civil fine of up to $200 for a first offense. If the violation is not corrected, or a correction plan is not submitted within seven calendar days of a second finding, the fine can reach $2,000, with each day the violation continues counted as a separate offense, and the county may also seek injunctive relief in court.

Frequently Asked Questions

What work requires a building permit in unincorporated York County?
Section 150.20 requires a permit before you construct, enlarge, alter, repair, move, demolish or change the occupancy of any building or structure, or install, alter, remove or replace an electrical, gas, mechanical or plumbing system regulated by the code. The owner or an authorized agent must apply to the Building and Codes Division and obtain the permit before starting work.
Does getting a permit mean my project is fully approved?
Not entirely. Section 150.26(B) treats an issued permit only as authorization to proceed with the specific approved work; it does not authorize violating, concealing or setting aside any code provision, and the Building and Codes Division can still require you to correct plan or construction errors discovered after the permit issues.
How long can I wait to start work after getting a building permit?
Up to 180 days. Section 150.26(E) voids a permit if work is not commenced and initially inspected within 180 days of issuance, or if it is later suspended or abandoned for 180 days, though the building official can grant one or more written extensions of up to 180 days each for cause.
Can York County revoke a building permit after it's issued?
Yes. Section 150.26(D) lets the building official revoke a permit issued based on a false statement or misrepresentation of a material fact in the application or plans. If that happens, no part of the permit fee is refunded, per the same subsection.

Sources & Official References

Other rules in York County

All York County rules

Compare York County to another location·View the South Carolina building safety overview

Get notified when Building Permits in York County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across York County