Shasta County, CA Building Safety: Building Permits (2026)
Key Facts
- Governing law
- Shasta County Code § 16.04.160
- Issuing agencies
- Building, Public Health, Fire Depts
- Permit voids
- work not started in 6 months
- Completion deadline
- 2 years from issuance
- Late-start penalty
- extra fee equal to permit fee
- Unpermitted work
- charged as a misdemeanor
Summary
Shasta County bars anyone from erecting, altering, moving, or converting a structure or mobile home, or installing, repairing, or replacing building service equipment such as wiring or piping, without first obtaining a valid permit. Code Section 16.04.160 lets the building department, public health department, and fire department issue these permits, and unpermitted work draws a misdemeanor charge plus a penalty fee.
A. No person shall erect, construct, enlarge, alter, repair, move, install, improve or convert a structure or mobile home, or any portion thereof, or install, alter, repair, replace or remodel any building service equipment regulated by this code or any code adopted by reference in this chapter, or cause the same to be done, without first obtaining a valid permit for such work when a permit is required by this chapter or by any code adopted by reference in this chapter, except as set forth in Section 16.04.020.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code: Supplement 22).
Full Breakdown
04, Article II of the county code. 160(B) directs the building department, department of public health, and fire department to issue permits and to standardize application forms and inspections. 160(C). 160(D). 190. 200(A). 200(B). 150 makes it unlawful to do any work requiring a permit without first obtaining one, or to occupy a structure under a changed use without a new certificate of occupancy.
Violations & Fines
Working without the required permit is a misdemeanor under Section 16.04.150(E). The code adds an administrative bite: Section 16.04.150(D) assesses an additional penalty fee equal to the amount of the original permit fee whenever work begins before a permit is issued, on top of the permit fee itself. Ignoring a stop-work order issued under this chapter, or changing a building's occupancy without a new certificate of occupancy, is also a violation the building official can cite separately.
Frequently Asked Questions
What happens if I build without a permit in Shasta County?
How long does a Shasta County building permit stay valid?
Which county office actually reviews my permit application?
Can I get an expired Shasta County permit reissued?
Sources & Official References
Other rules in Shasta County
California rules heatmap·Compare Shasta County to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.