Key Facts

Enforcement agency
Owensboro Metropolitan Planning Commission (§ 5-16)
Base fee
$20 for work valued up to $3,000
Late-start penalty
Fees double if work starts before the permit issues
Building move fee
$50 flat fee (§ 5-19(c)(3))
Plans required
At least 2 scaled copies with the application

Summary

In the City of Owensboro, Owensboro Municipal Code § 5-18 makes it unlawful to construct, enlarge, alter, or change any building or structure without first filing a written permit application with the city building official, scaled plans in hand and the required fee paid. The Owensboro Metropolitan Planning Commission enforces the Kentucky Building Code and sets the permit fee schedule under §§ 5-16 and 5-19.

Sec. 5-16. - Enforcement agency.(a)The Owensboro Metropolitan Planning Commission is designated the local enforcement agency for codes referenced in this article. ... ... Sec. 5-18. - Permits.(a)It shall be unlawful to construct, enlarge, alter or change a building or structure without filing a written application for a permit with the city building official. ... Any excavation or any change or alteration other than ordinary general repair will constitute the beginning of work for which a building permit shall be required. ... The application ... for permit shall be accompanied by the required fee. ... ... Sec. 5-19. - Fees.(a)General: No permit will be issued until the fees prescribed in this section have been paid. ( ... c) ... (5)Double fee: Where work for which a permit is required by this article is started or proceeded with prior to obtaining the permit, the fees herein specified shall be doubled.

Full Breakdown

The Owensboro Metropolitan Planning Commission (OMPC) is the local enforcement agency for the Kentucky Building Code chapter under § 5-16, and it fixes the building permit fee schedule, subject to city board of commissioners approval, and collects and accounts for every permit fee the city charges. Section 5-18 requires a written application before any construction, enlargement, alteration, or change to a building or structure; simply staking out a site does not start the clock, but any excavation or change other than ordinary general repair does, and the application must include at least two sets of scaled plans and specifications plus the required fee.

The building official rejects a nonconforming application in writing with reasons, or issues the permit as soon as practicable, and a copy must stay on the job site for public inspection until the work is finished. Section 5-19 sets a tiered fee schedule keyed to the total valuation of the work, starting at $20 for jobs up to $3,000 and rising in graduated increments, as low as $0.50 per additional $1,000, for work above $10 million; the OMPC's inspection department maintains a construction-cost chart tied to the Kentucky Building Code's Table 505 to value each project.

Buildings that fall under city jurisdiction while already under construction must obtain a permit and pay the pro-rata fee for the unfinished portion. Moving an entire building carries its own $50 fee under § 5-19(c)(3), and remodeling, converting, or altering an existing structure needs its own permit under § 5-22, though ordinary repairs and seasonal maintenance are excluded.

Violations & Fines

Starting or continuing permitted work before obtaining the permit doubles every fee due under § 5-19(c)(5), and that double fee does not excuse compliance with the rest of the article or shield the violator from any other penalty the code allows. Remodeling or altering a residential structure without the required notice and permit under § 5-22 is itself a separate offense, enforceable under the code's general penalty provisions.

Frequently Asked Questions

What triggers the need for a building permit in Owensboro?
Owensboro Municipal Code § 5-18 requires a permit before you construct, enlarge, alter, or change any building or structure; staking out the site doesn't count, but excavation or any change beyond ordinary general repair does start the clock and requires the permit first.
Who reviews and issues Owensboro building permits?
The Owensboro Metropolitan Planning Commission is the designated local enforcement agency under § 5-16, and it sets the permit fee schedule, subject to the board of commissioners' approval, and reviews the application, plans, and specifications the city building official requires under § 5-18.
How much does an Owensboro building permit cost?
Section 5-19 uses a sliding scale based on the value of the work: $20 covers projects up to $3,000, then $3 per additional $1,000 up to $100,000, dropping to $2 and eventually $0.50 per $1,000 as the valuation climbs past $500,000 and $10 million.
What happens if I start construction before getting a permit?
Section 5-19(c)(5) doubles every fee owed on work started or continued before the permit is obtained, and paying the double fee does not excuse the builder from otherwise complying with the article or from any other penalty the code allows.

Sources & Official References

Other rules in Owensboro

All Owensboro rules

Compare Owensboro to another location·View the Kentucky building safety overview

Get notified when Building Permits in Owensboro, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.