Key Facts

Governing rule
SCC 3.02.020, permit required
Application standard
IBC Section 105.3
Permit expiration
3 years from issuance
Extension available
one 180-day extension
Non-building permits expire
18 months from issuance
Enforcement agency
Building & Planning director, sheriff citations
Appeal path
SCC Chapter 1.46 hearing examiner

Summary

Spokane County Code 3.02.020 makes it unlawful to erect, alter, repair, move, or demolish any building, structure, mechanical, or plumbing system in the unincorporated county without a separate permit from the building official first. Applications must meet IBC Section 105.3, pay processing, land-use, and plan-review fees, and permits expire three years after issuance.

These county ordinances apply to unincorporated areas of Spokane County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)General. It shall be unlawful for any person, firm or corporation to erect, construct, install, enlarge, alter, repair, move, improve, remove, convert, demolish, replace, use or occupy any building, structure, mechanical system or plumbing system regulated by this title, unless exempted by the codes adopted by this title, or cause the same to be done without first obtaining a separate permit for each building, structure or system installation from the building official.(b)Application. For the purpose of this title, and the provisions of RCW 19.27.095(2) the requirements for a fully completed application for a building permit are delineated in Section 105.3 of the IBC and shall require payment of all processing, land use, and plan review fees. Building permits shall automatically expire and become invalid by limitation of time three years from the date of permit issuance. The director is authorized within his/her discretion to grant one extension of time, for a period not to exceed one hundred eighty days.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 63).

Full Breakdown

010). 020(a) makes it unlawful to erect, construct, install, enlarge, alter, repair, move, improve, remove, convert, demolish, replace, use or occupy any building, structure, mechanical system or plumbing system regulated by the title without first obtaining a separate permit for each building, structure or system installation from the building official. 020(b)). 020(c)). Operational fire permits under the International Fire Code are exempt from those expiration limits. 020(d)). 040).

Violations & Fines

Building without a required permit is a code violation the building director enforces directly: Section 3.02.010(b) lets the director call on the Spokane County Sheriff to issue criminal citations for violations of Title 3, and the director can record a notice of noncompliance against the property with the county auditor when an owner will not bring unpermitted work into conformance. Appeals of any building official decision, order, or determination go through the Chapter 1.46 hearing examiner process, not district court.

Frequently Asked Questions

Do I need a permit to remodel a house in unincorporated Spokane County?
Yes. Section 3.02.020(a) makes it unlawful to erect, alter, repair, or convert any building or system regulated by Title 3 without first getting a separate permit from the building official, and the application must meet IBC Section 105.3 plus pay processing, land-use, and plan-review fees.
How long is a Spokane County building permit good for?
Three years from the date of issuance. The director can grant one extension of up to 180 days if you ask in writing before the permit expires and show just cause, per Section 3.02.020(c); permits unrelated to building construction expire in eighteen months instead.
What happens if my permit expires before I finish construction?
Work must stop immediately under Section 3.02.020(d). If the scope of the project has not changed, a new permit issues once you submit a complete application and pay current prorated inspection fees; a changed scope requires paying full current application and plan-review fees again.
Who enforces Spokane County's building permit requirement?
The county department of building and planning's building director, designated the building official, code official, and fire code official under Section 3.02.010. The director may ask the Spokane County Sheriff to issue a criminal citation for a Title 3 violation and can record noncompliance notices with the county auditor.

Sources & Official References

Other rules in Spokane County

All Spokane County rules

Compare Spokane County to another location·View the Washington building safety overview

Get notified when Building Permits in Spokane County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across Spokane County