Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Permit issuer
Building official, Department of Transportation and Public Works
Shed exemption
One-story, up to 120 square feet of floor area
Fence exemption
Up to 7 feet in rear or side yards, not around pools
Permit expiration
180 days without start, or 180 days suspended
No-permit penalty cap
Greater of $500 or 1 percent of construction cost
Court penalty
Fine up to $1,000, up to 90 days, or both
Appeal deadline
30 days after notice of the decision

Summary

St. Louis County requires a permit from the building official before anyone builds, enlarges, alters, repairs, moves or demolishes a structure, changes its occupancy, paves a parking lot for anything but a single-family home, or touches electrical, gas, mechanical or plumbing systems. Sheds up to 120 square feet and fences up to 7 feet in rear or side yards are exempt. Starting without a permit costs up to the greater of $500 or 1 percent of construction cost.

City-specific rules exist: Florissant has its own building permits rules that differ from St. Louis County's county-level regulations. If you live in Florissant, check the city-specific page instead.

105.1 Required. Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, ... or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the building official and obtain the required permit. ... 105.2 Work exempt from permit. Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following: Building: ... 4. New fencing or replacement of existing fencing not more than 7 feet (2134 mm) in height, except when enclosing swimming pools, spas, or hot tubs, in the rear or side yards. ... 9. Movable cases, counters and similar fixtures not over 5 feet 9 inches (1753 mm) in height.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 | Traffic: Supplement 80).

Full Breakdown

Section 105.1 of the Building Code of St. Louis County, enacted through County Code § 1115.101, puts the duty on the owner or the owner's authorized agent: apply to the building official and hold the permit before work starts. The trigger list covers constructing, enlarging, altering, repairing, moving or demolishing a building, changing its occupancy, installing or altering a ground level paved parking lot (other than one serving a single-family dwelling), and establishing a new or relocated lot line that affects an existing structure. Electrical, gas, mechanical and plumbing work is covered too.

Section 105.2 lists the exemptions, and none of them excuses a code violation. One-story detached sheds and playhouses need no permit up to 120 square feet of floor area. New or replacement fencing up to 7 feet high in rear or side yards is exempt, but fences around pools, spas or hot tubs, and any fence using electrified components, barbed wire or razor ribbon, are not. Retaining walls up to 3 feet high are exempt (2 feet if they support a surcharge or impound Class I, II or III-A liquids), yet a permit is required when the wall sits within its own height of the property line or when wall plus guard or fence passes 6 feet. Prefabricated above-ground pools are exempt only at a maximum depth of 24 inches and 5,000 gallons. Awnings projecting no more than 54 inches and finish work like painting and carpeting also need no permit.

Reroofing needs a permit on roofs sloped under 4:12, and any change in roof covering system needs a permit, plans and specifications at any slope. Temporary buildings need a temporary structures permit under Section 3103 of the International Building Code. Disaster repairs need a Disaster Damage Repair Permit, discounted or free at the building official's discretion if issued within 90 days after the disaster ends, and the work must finish within one year.

An application is abandoned 180 days after filing unless pursued in good faith, with extensions of up to 90 days each. An issued permit expires if work does not begin within 180 days or stops for 180 days, with extensions of up to 180 days each. Demolition permits expire if work does not start within 30 days or finish within 90 days. A permit is not valid until the Chapter 1100 fees are paid.

Violations & Fines

Section 114.4 makes it unlawful to start permitted work without a permit, keep working after a stop work order, or skip a required inspection. The building official can issue a stop work order and assess a no-permit penalty of up to the greater of $500 or 1 percent of the cost of construction, and a no-inspection penalty of up to $500. A court can fine up to $1,000, order up to 90 days in jail, or both, and each day after notice counts as a separate offense.

Frequently Asked Questions

Do I need a permit for a backyard shed in St. Louis County?
Not if it is a one-story detached accessory structure used as a tool or storage shed or playhouse and the floor area is 120 square feet or less. A larger shed needs a permit. The exemption never excuses a violation of the building code or any other ordinance, so setbacks and zoning rules still apply to where it sits.
How long does a St. Louis County building permit last?
A permit becomes invalid if the work does not begin within 180 days after issuance, or if work is suspended or abandoned for 180 days. The building official can grant written extensions of up to 180 days each once you show justifiable cause. Demolition permits are shorter: work must start within 30 days and finish within 90 days of issuance.
What is the penalty for building without a permit?
The building official can issue a stop work order and assess a no-permit penalty of no more than the greater of $500 or 1 percent of the cost of construction, on top of the permit fees. The stop work order stays in force until the penalty is paid and the permit requirements are met. A court can also fine up to $1,000 or impose up to 90 days in jail.
Can I appeal a no-permit penalty or a permit decision?
Yes. The Building Commission sits as the Board of Appeals. File a written application with the building official within 30 days after you are notified of the decision, with the Chapter 1100 filing fee. The board meets within 30 days of the notice, and you can pay the assessed penalty before the hearing to cancel it. Board decisions are open to judicial review under Chapter 536 RSMo.
Do I need a permit to replace my roof?
Yes, in the two situations the code names. Reroofing a slope of less than 4:12 needs a permit, and any change in the roof covering system needs a permit, plans and specifications regardless of slope. For a low-slope reroof, plans and specifications are required only below one-quarter unit vertical in 12 horizontal. The reroofing permit fee is set in Chapter 1100.

Sources & Official References

Other rules in St. Louis County

All St. Louis County rules

Compare St. Louis County to another location·View the Missouri building safety overview

Get notified when Building Permits in St. Louis County, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across St. Louis County