Key Facts

Adopted code
CA Electrical Code 2025, Part 3 (§18.04.025(D))
Application abandoned
After 1 year of inactivity
Permit expires
After 1 year without approved inspection
Extensions
Up to 180 days each, written request
Refunds
Up to 80% of permit/plan-review fee
Local electrical board
Abolished under §18.04.045

Summary

Mendocino County adopts the 2025 California Electrical Code at County Code § 18.04.025(D) and rewrites its Annex H permit rules at § 18.04.045: applications lapse after a year of inactivity, permits expire without a yearly inspection, and the Building Official can grant 180-day extensions or an 80% fee refund on withdrawn work.

These county ordinances apply to unincorporated areas of Mendocino County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(4)Time limitation of application. A permit application for any proposed work shall be deemed to have been abandoned one (1) year after the date of filing, unless such application has been pursued in good faith as determined by the Building Official. The applicant must request an extension in writing, and demonstrate justifiable cause. The Building Official may grant one or more extensions in time, for periods of not more than 180 days each. Each extension requires payment of a fee established by the Board of Supervisors.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 75).

Full Breakdown

045 rewrites several Annex H sections to fit county procedure. 15, which would have created a separate Electrical Board, "is deleted," leaving the Building Official as sole authority. 19(H) adds that "a permit application for any proposed work shall be deemed to have been abandoned one (1) year after the date of filing, unless such application has been pursued in good faith," with the Building Official able to grant extensions "for periods of not more than 180 days each" once the applicant requests one in writing and shows "justifiable cause," paying a fee the Board of Supervisors sets.

and an inspection resulting in an approval of the work has not been obtained," or if a full year passes between approved inspections; permits lapsed under five years can be reinstated for a fee. 19(E) lets the Building Official refund an erroneously collected fee in full, or up to 80 percent of a permit or plan-review fee on written request filed within a year. 23(B)(3)).

Violations & Fines

An electrical permit that lapses under § 80.19(H), or work done without one, falls under the same Title 18 enforcement as other building violations: § 18.08.030 imposes a violation fee equal to the normal permit fee if self-reported, double if the County discovers unpermitted work by complaint, and triple for commercial or industrial work, on top of infraction penalties under § 18.04.075 and Government Code § 25132, assessed as a new offense each week the citation remains uncorrected.

Frequently Asked Questions

How long is an electrical permit good for in unincorporated Mendocino County?
One year. Under the county's amendment to Annex H § 80.19(H), "every permit issued shall become invalid if the work... is not commenced within one (1) year (365 calendar days)... and an inspection resulting in an approval of the work has not been obtained," and the same one-year clock applies between approved inspections after that.
Can I get an extension on an expiring electrical permit?
Yes. The Building Official may grant one or more extensions of up to 180 days each, but you must request it in writing and show "justifiable cause," and each extension requires paying a fee the Board of Supervisors has set. Permits lapsed under five years can also be reinstated for a reinstatement fee.
Is there a separate Electrical Board that reviews permits?
No. Section 18.04.045 deletes Annex H § 80.15, the section that would have created an Electrical Board, so the Building Official in the Department of Planning and Building Services holds sole authority over electrical permit review, inspection, and appeals under the county's amended Annex H.

Sources & Official References

Other rules in Mendocino County

All Mendocino County rules

California rules heatmap·Compare Mendocino County to another location·View the California building safety overview

Get notified when Electrical Permits in Mendocino County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.