Key Facts

Permit issuer
director of inspection services
Low-voltage exemption
≤50 volts and ≤1,000 watts signal wiring
Contractor requirement
must hold state electrical contractor's license
Penalty for no permit
misdemeanor
Inspection window
director inspects within 24 hrs of completion notice

Summary

Any electrical wiring, device, appliance, or equipment installed or altered in Durham needs a permit from the director of inspection services first, under City Code § 10-107. A narrow low-voltage exemption exists, but the permittee must hold a state electrical contractor's license, and skipping the permit is a misdemeanor.

Except as otherwise provided, no electric wiring, devices, appliances or equipment shall be installed within or on any building, structure or premises, nor shall any alteration be made in any such existing wiring, devices, appliances or equipment unless a permit therefor shall first have been secured from the director of inspection services. In addition to any other remedy available in the Code, violation of this section is a misdemeanor.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 36).

Full Breakdown

Sec. 10-107 is the general permit requirement for electrical work in Durham: except as otherwise provided, no electric wiring, device, appliance, or equipment may be installed in or on a building, structure, or premises, and no alteration may be made to existing wiring or equipment, unless a permit has first been secured from the director of inspection services. Two narrow exemptions carve out permit-free work: Sec. 10-108 excuses signal or intelligence-transmission wiring that operates at 50 volts or less and doesn't include generating or transforming equipment capable of supplying more than 1,000 watts, and Sec.

10-109 excuses public service corporations installing equipment needed to generate, transmit, and distribute electrical energy to their own customers. Beyond the permit itself, Sec. 10-112 requires that no permit be issued to anyone who isn't the holder of a state electrical contractor's license, and that licensee must also give the surety bond required under Sec. 10-89. Once work is done, Sec. 10-117 requires the installer to notify the director, who inspects within 24 hours if practicable, and Sec. 10-119 separately bars concealing wiring behind permanent building surfaces until the director has inspected and approved it, a requirement whose violation is also charged as a misdemeanor.

A contractor who doesn't correct a defect within 48 hours of notice from the electrical inspector loses the ability to get further permits until it's fixed (Sec. 10-113), and anyone who fails to pay required fees is likewise cut off from new permits (Sec. 10-116).

Violations & Fines

Installing or altering electrical wiring or equipment without the Sec. 10-107 permit is a misdemeanor, as is concealing wiring before the required pre-concealment inspection under Sec. 10-119. The director can also withhold further permits from a contractor who fails to correct a cited defect within 48 hours of notice, or who falls behind on required fees.

Frequently Asked Questions

Do I need a permit to add a new circuit or outlet in Durham?
Yes. Sec. 10-107 requires a permit from the director of inspection services before any electric wiring, device, or equipment is installed or altered, with only a narrow exemption for low-voltage signal wiring under 50 volts and 1,000 watts.
Can I do my own electrical work under a Durham permit?
Only a person holding a state electrical contractor's license can be issued a permit under Sec. 10-112, and that licensee must also carry the surety bond required by Sec. 10-89 before securing permits for wiring installation, alteration, or repair.
What if my electrical inspection reveals a defect?
Sec. 10-113 gives you 48 hours after notice from the electrical inspector to correct the defect. Until it's fixed, the director will not issue further permits for the property, and concealing uninspected wiring is itself a separate misdemeanor under Sec. 10-119.

Sources & Official References

Other rules in Durham

All Durham rules

Compare Durham to another location·View the North Carolina building safety overview

Get notified when Electrical Permits in Durham, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.