Key Facts
- Code adopted
- National Electrical Code (15.08.050)
- Advance notice required
- 24 hours before starting work
- Enforcing officer
- Electrical inspector, fire department
- Current cannot be energized
- Until certificate of satisfactory inspection issued
- General penalty
- Up to $300 per offense (1.16.010)
Summary
Lawrence adopts the National Electrical Code for all wiring work and requires a permit and inspection before any current is turned on. Municipal Code 15.08.170 requires 24-hour written notice to the electrical inspector before starting work, and 15.08.200 charges a fee for every permit and inspection.
15.08.050 - National Electrical Code adopted—Enforcement. The National Board of Fire Underwriters Code for electric wiring and apparatus, as recommended by the National Fire Protection Association, is adopted. ... 15.08.170 - Written notice to inspector required prior to commencing work. No person or agent thereof shall commence any new work, additions, alterations or extensions to old work, in or upon any building or other structure in the city, until written notice thereof shall have been given to the electrical inspector at least 24 hours before the work is started. ... 15.08.200 - Fees for permits and inspections. A fee shall be charged for each permit and inspection of any premises wired for the use of electricity for light, heat or power purposes, or for the transmission of signals by electricity.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 8).
Full Breakdown
050). 030). 170). 180). 200). 00, among other line items. 190).
Violations & Fines
Interfering with the electrical inspector or an assistant while performing official duties is prohibited under 15.08.130. Wires or apparatus found in a dangerous or unsafe condition after the annual inspection required by 15.08.160 must be repaired within a reasonable time of written notice; failing, neglecting or refusing to do so "shall be deemed guilty of violation of this chapter." Chapter violations are punishable under the citywide general penalty, Section 1.16.010, up to $300.00 per offense under General Laws Chapter 40, Section 21D, with each day of continued violation a separate offense.
Frequently Asked Questions
What electrical code does Lawrence enforce?
How much notice do I need to give before starting electrical work?
Can I turn on power before the electrical inspection is done?
Are there separate fees for electrical permits and inspections?
Sources & Official References
Other rules in Lawrence
Compare Lawrence to another location·View the Massachusetts building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.