Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
McCracken County Code § 71.02
Base permit fee
$25, due before work begins
Plan review fee
$125 if a review is required
Re-inspection fee
$100 per return trip
Large-project fee
2% down to 1% of value over $25,000
Inspector
Certified electrical inspector under Fiscal Court contract

Summary

Electrical work in unincorporated McCracken County needs a permit before work begins, with the fee set at $25 under Code § 71.02(B); the County Fiscal Court contracts with a certified electrical inspector to handle plan review and inspections for new construction, additions, remodels, repairs and upgrades.

These county ordinances apply to unincorporated areas of McCracken County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(A) The County Fiscal Court may contract with a certified electrical inspector to provide electrical plan review and inspection services for new construction, additions, remodels, repairs, upgrades, and other projects requiring electrical permits. (B) An electrical permit fee shall be required before any electric work commences, with the fee set at $25.

Full Breakdown

Section 71.02 of the McCracken County Code governs electrical permitting separately from the general building permit fee schedule in § 71.01. Under § 71.02(A), the County Fiscal Court contracts with a certified electrical inspector to provide plan review and inspection services for new construction, additions, remodels, repairs, upgrades and other projects that require an electrical permit. Division (B) requires the permit fee to be paid before any electrical work commences, and sets that base fee at $25; the electrical contractor, property owner or other responsible person must pay all fees to the inspector, who is responsible for collecting them under (C).

No certificate of inspection, compliance or other final approval can be issued under (D) until every required fee is paid. Beyond the flat $25 permit fee, § 71.02(F) layers on work-specific charges: $125 for an electrical plan review if one is required, $75 for a certificate-of-occupancy inspection on an existing building, and a $100 charge for each return trip the inspector has to make because previously-flagged work was not finished on schedule. For larger jobs, the fee scales with the completed value of the work: $125 if the work is valued under $8,000, $250 between $8,000 and $16,500, $500 between $16,500 and $25,000, and a percentage schedule above $25,000 running from 2% down to 1% as the project value rises through the $200,000, $300,000, $500,000 and $700,000 brackets. Copies of the inspection documentation and compliance certificate go to the County Inspection Department under (E).

Violations & Fines

Starting electrical work without paying the § 71.02(B) permit fee, or before the required inspections and certificate of compliance are issued under (D), leaves the work unauthorized under Chapter 71; the electrical inspector can withhold the certificate of occupancy until all fees are paid. Unpermitted electrical work performed as part of a broader building project is enforced under the general § 70.99 penalty of $10 to $1,000, assessed per day the violation continues.

Frequently Asked Questions

How much is an electrical permit in McCracken County?
Section 71.02(B) sets the base electrical permit fee at $25, due before any electrical work begins. Depending on the job, additional charges apply: $125 for a plan review if required, and value-based inspection fees ranging from $125 for work under $8,000 up to a percentage schedule for projects over $25,000.
Who inspects electrical work in the county?
The County Fiscal Court contracts with a certified electrical inspector under § 71.02(A) to handle plan review and inspection for new construction, additions, remodels, repairs and upgrades that require an electrical permit; that inspector also collects the required fees.
What if the inspector has to come back for incomplete work?
Section 71.02(F)(3) allows the inspector to charge an additional $100 for each trip needed to re-inspect work that should have been finished within the allotted time frame but was not, on top of the original permit and inspection fees.

Sources & Official References

Other rules in McCracken County

All McCracken County rules

Compare McCracken County to another location·View the Kentucky building safety overview

Get notified when Electrical Permits in McCracken County, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.