Washington County, UT Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- National Electrical Code, State of Utah amended version
- Governing section
- County Code § 9-1-4
- Enforcing office
- Washington County building inspector
- Appeal body
- 5-member Board of Building Appeals, 5-year terms
- Default penalty
- Class B misdemeanor, up to $1,000 fine
Summary
Washington County adopts the National Electrical Code, as amended by the State of Utah, as part of its Building Code under County Code section 9-1-4. Anyone wiring, altering, or repairing electrical systems in the unincorporated county needs a permit from the county building inspector before starting work.
The most recent version adopted by the State of Utah of the following codes and the appendices and the State's amendment are incorporated by reference and adopted as the Building Codes of Washington County: International Building Code including appendix J, International Mechanical Code, International Fuel Gas Code, International Residential Code including appendix J, International Fire Code including appendices A, B, C, and D as amended by the State of Utah, International Energy Conservation Code, International Plumbing Code, National Electrical Code, HUD Code, and the Model Manufactured Home Installation Standard.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-17: Code current through: Ord. 2026-1329-O, passed 8-18-2026).
Full Breakdown
Section 9-1-4 of the Washington County Code adopts by reference the most recent State of Utah version of the National Electrical Code, alongside the International Building, Residential, Mechanical, Fuel Gas, Fire, Energy Conservation and Plumbing Codes, the HUD Code, and the Model Manufactured Home Installation Standard, as the county's Building Codes. Three copies of each adopted code are kept on file at the Office of the Washington County Clerk for public review. Under section 9-1-7, no building permit, including one covering electrical work performed as part of construction, alteration or repair, can be issued unless the project meets the adopted building codes, the county zoning ordinance, the subdivision ordinance and the groundwater protection ordinance.
Permit, plan review and investigation fees are set in the fee table adopted by the county commission under section 9-1-8, and no certificate of occupancy can be issued under section 9-1-9 until the wiring passes inspection for compliance with the adopted National Electrical Code. The county building inspector administers and enforces the chapter under section 9-1-10, and has no discretion to impose requirements beyond what the adopted codes and county ordinances specify, per section 9-1-11. A property owner who disputes how the building inspector applied the code can appeal to the five-member board of building appeals created under section 9-1-12, whose members serve staggered five-year terms, or appeal in the manner set out in Title 10, Chapter 2, under section 9-1-13.
Violations & Fines
Wiring work performed without the required permit, or work that ignores the adopted National Electrical Code, violates section 9-1-5's ban on constructing, altering or repairing any structure without complying with the adopted codes. Because Title 9 sets no separate penalty, a violation defaults to the county's general penalty clause, section 1-4-1: a class B misdemeanor punishable by up to six months in jail and a fine up to $1,000.00 for an individual.
Frequently Asked Questions
Does Washington County require an electrical permit for new wiring?
Which electrical code edition applies in unincorporated Washington County?
What happens if electrical work is done without a permit?
Sources & Official References
Other rules in Washington County
Compare Washington County to another location·View the Utah building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.