Key Facts

Adopted code
2020 National Electrical Code
Adopting sections
§§ 6-3, 6-5, 6-7
Electric service permit expiration
180 days, § 105.5
Last amended
Ord. 21-475, Nov. 9, 2021
Unpermitted work penalty
fee doubled, § 6-12(P)
Administered by
Building & Community Services Division

Summary

Kane County requires electrical work in the unincorporated area to comply with the 2020 National Electrical Code, adopted alongside the 2021 International Building, Residential, Mechanical and Existing Building Codes. A building permit covering the electrical work is issued by the county's Building & Community Services Division and follows the same fee schedule as other construction.

City-specific rules exist: Elgin, and Aurora have their own electrical permits rules that differ from Kane County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

6-5: ADOPTION OF ALL OTHER NEW CONSTRUCTION CODES: 2021 International Building Code 2021 International Mechanical Code 2018 International Energy Conservation Code as published by the International Code Council, 5203 Leesburg Pike, Suite 600, Falls Church, Virginia, 22041-3401 2020 National Electrical Code as published by the National Fire Protection Association, Inc., One Batterymarch Park, Quincy, Massachusetts, 02269. (Ord. 12-366, 12-11-2012, eff. 1-1-2013; amd. Ord. 21-475, 11-9-2021)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-17: Code current through: Ord. 26-183, passed 4-14-2026).

Full Breakdown

' The same 2020 NEC edition is separately adopted for one- and two-family residences and accessory structures under section 6-3, and again for existing buildings under section 6-7, so every electrical installation in unincorporated Kane County, new or existing, residential or otherwise, is measured against the identical 2020 NEC standard regardless of building type. 8. 5 whose permits expire 180 days after issuance rather than the standard two-year window, so an electrician or homeowner has six months to complete the installation once the permit is pulled before needing an extension or a new permit.

These adoptions were most recently amended by Ordinance 21-475 on November 9, 2021, updating the county to the 2020 NEC and the 2021 International Code Council editions currently in force.

Violations & Fines

Performing electrical work without a permit that conforms to the adopted 2020 National Electrical Code, or letting an electric-service permit lapse past its 180-day expiration under section 105.5, is enforced as a Kane County Code violation: unpermitted work doubles the applicable fee under section 6-12(P), and continuing noncompliance carries the general fine of up to $500 per day under section 1-11.

Frequently Asked Questions

What electrical code does Kane County enforce?
The 2020 National Electrical Code, as published by the National Fire Protection Association. Section 6-5 adopts it for new construction, section 6-3 adopts the same edition for one- and two-family residences, and section 6-7 adopts it again for work on existing buildings.
How long is an electrical permit good for?
Electric service permits expire 180 days after issuance under section 105.5, the same shortened window that applies to pools, decks, and accessory structures, rather than the two-year expiration that applies to general construction permits.
Can I do the electrical work myself before pulling a permit?
You can do the work, but starting before the permit is issued doubles the fee you owe under section 6-12(P), and the installation still has to conform to the 2020 NEC and pass inspection under Section 110 before it can be approved.
When did Kane County update to the 2020 NEC?
Ordinance 21-475, adopted November 9, 2021, updated the county's electrical, building, residential, mechanical, and existing building code adoptions, including the move to the 2020 National Electrical Code and the 2021 International Code Council family of codes.

Sources & Official References

Other rules in Kane County

All Kane County rules

Compare Kane County to another location·View the Illinois building safety overview

Get notified when Electrical Permits in Kane County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Kane County