Key Facts

Adopted code
2025 California Electrical Code, Title 24 Part 3
Permit exemptions
Minor repairs, lamp replacement, plug-in portable equipment
Accessory building exception
120 sq ft or less on same lot
Unpermitted work penalty
Double permit fee under Section 17.24.130
Inspection rule
No concealing or energizing before department approval
Appeal path
Board of Building Appeals, then Board of Supervisors

Summary

Installing, energizing or altering electrical equipment or wiring anywhere in unincorporated Kern County requires a permit from the building official under Section 17.24.090, with narrow exceptions for minor repairs and lamp replacement. A separate permit covers each building, unpermitted work doubles the fee, and utilities cannot legally energize wiring the county hasn't inspected.

City-specific rules exist: Bakersfield, and Ridgecrest have their own electrical permits rules that differ from Kern County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

17.24.090 - Permits required. It shall be unlawful for any person, firm, corporation, owner of the land, or possessor to install, energize, re-energize, use or maintain any electrical equipment or wiring system within or on any building, structure, or premises within the jurisdiction of the enforcing official, nor shall any alteration or addition be made thereto, without first securing a permit therefor from the building official, with the following exceptions: A.Minor repair work, the replacement of lamps or the connection of portable electrical equipment to suitable permanently installed receptacles;B.Electrical wiring expressly exempted from this chapter; (see Section 17.24.030).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 59 Update 1).

Full Breakdown

090 makes it "unlawful for any person, firm, corporation, owner of the land, or possessor to install, energize, re-energize, use or maintain any electrical equipment or wiring system" without first securing a permit, exempting only minor repair work, lamp replacement, and connecting portable equipment to existing permanent receptacles. 100 requires a separate permit for each building, though a main dwelling's permit can also cover wiring for an accessory building of 120 square feet or less on the same lot when supplied from the main building.

150 requires two sets of plans (three outside the Bakersfield office) drawn no smaller than one-eighth inch to the foot. 190 bars anyone from energizing unapproved work and bars utilities from supplying power to a wiring system that hasn't been inspected, or where the meter or service drop has been removed, until the department approves it. 160's further right of appeal to the Board of Supervisors.

Violations & Fines

Section 17.24.130 doubles the permit fee for anyone who "commences any electrical work for which a permit is required... without first having obtained a permit," unless the building official finds it was urgent emergency work, in which case a permit must still follow as soon as practical or the double fee applies for unreasonable delay. Beyond the fee, Section 17.04.200's Title 17 misdemeanor penalty, up to $1,000 and six months in county jail, backs every electrical permit violation.

Frequently Asked Questions

Do I need a permit to rewire an outlet in unincorporated Kern County?
Yes, unless it's minor repair work or you're just replacing a lamp or plugging portable equipment into an existing permanent receptacle. Section 17.24.090 makes installing, energizing or altering any electrical equipment or wiring unlawful without a permit from the building official first, and each building needs its own permit under Section 17.24.100.
Can a small shed skip its own electrical permit?
Only partly. Section 17.24.100 lets a dwelling's electrical permit also cover wiring for one accessory building on the same lot, but only if that building is 120 square feet or less and its power is supplied from the main building; anything larger needs its own separate electrical permit.
What happens if I energize new wiring before it's inspected?
Section 17.24.190 makes it unlawful to use or energize electrical work installed under a permit until the department has inspected and approved it, and bars utility companies from supplying power to it as well; combined with Section 17.04.200, doing so anyway risks a misdemeanor charge and up to $1,000 in fines.
What if I start electrical work without getting a permit first?
Section 17.24.130 doubles the required permit fee for anyone who begins electrical work before obtaining the permit, unless the building official finds it was genuine emergency work; either way a permit must still be obtained as soon as practical, and Section 17.04.200 can add misdemeanor penalties for continued noncompliance.

Sources & Official References

Other rules in Kern County

All Kern County rules

California rules heatmap·Compare Kern County to another location·View the California building safety overview

Get notified when Electrical Permits in Kern County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Kern County