Key Facts

Adopted code
National Electrical Code, 2020 Edition
Permit issuer
Dept. of Electrical Inspection
First violation fine
up to $200
Repeat violation fine
up to $2,000 per day
Permit-exempt work
5 minor categories under § 401.3
Application expires
180 days if abandoned

Summary

Unincorporated Greenville County requires an electrical permit under the 2020 National Electrical Code before installing, altering or replacing electrical systems or equipment. A first violation draws a civil penalty of up to $200, rising to $2,000 per day if not corrected within seven calendar days, and a short list of minor jobs is exempt from the permit requirement.

These county ordinances apply to unincorporated areas of Greenville County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

401.1 Permits Required. Permits required by this code shall be obtained from the code official. Permit fees, if any, shall be paid prior to issuance of the permit. 401.2 Types of permits. An owner, authorized agent or contractor who desires to ... erect, install, enlarge, alter, repair, remove, convert or replace electrical systems or equipment, the installation of which is regulated by this code ... shall first make application to the code official and obtain the required permit for the work. ... SECTION 1003 PENALTIES (1) Any person found to be in violation of the provisions of the Electrical Code ... may be cited and assessed, by civil penalty, an amount not more than two hundred dollars. Before being charged with a second violation, the person must be given seven calendar days to remedy the violation or submit an acceptable plan for correcting the violation. (2) A person who fails to correct a violation ... may be cited and assessed, by civil penalty, an amount not to exceed two thousand dollars. Each day a violation continues is a separate offense.

Full Breakdown

1 requires anyone who wants to erect, install, alter, repair, remove, convert or replace electrical systems or equipment regulated by the code to first make application to the code official and obtain a permit; fees, where charged, must be paid before the permit issues, and the issued permit must stay on the premises and be available for inspection. 3 exempts five categories of minor work from the permit requirement: listed cord-and-plug temporary decorative lighting, reinstalling attachment-plug receptacles (though not the outlets), repairing or replacing branch-circuit overcurrent devices of the same capacity in the same location, temporary experimental-laboratory wiring, and wiring or equipment operating under 25 volts and 50 watts.

That exemption does not authorize work that otherwise violates the code. 5 deems an unpursued application abandoned after 180 days, though the code official can grant extensions of up to 90 days each on written request. Chapter 10 of the same administrative code makes it unlawful under Section 1001 to erect, alter or repair any regulated electrical system in violation of the code, and Section 1003 sets the same two-tier penalty used across the county's construction codes: up to $200 for a first violation, with seven calendar days to correct it, and up to $2,000 per day for an uncorrected second violation. 3.

Violations & Fines

A first electrical code violation carries a civil penalty of up to $200, with seven calendar days to fix it or submit a correction plan before a second citation issues. A second, uncorrected violation can reach $2,000, and each additional day counts as a separate offense under Section 1003. Unpermitted or unsafe work also violates Section 1001's unlawful-acts provision, and the code official can request legal counsel to seek a court order restraining or abating it.

Frequently Asked Questions

Do I need a permit for electrical work in unincorporated Greenville County?
Yes, unless the work falls into one of the five exemptions in Section 401.3 (temporary decorative lighting, receptacle reinstallation, same-capacity overcurrent device replacement, experimental lab wiring, or under-25-volt/50-watt equipment). Everything else regulated by the 2020 National Electrical Code needs a permit from the code official first.
What happens if my electrical permit application sits unused?
Section 402.5 deems it abandoned 180 days after filing unless you've pursued it in good faith or already gotten the permit. The code official can grant extensions of up to 90 days each, but you have to request the extension in writing and show justifiable cause.
How much can an electrical code violation cost in Greenville County?
A first violation carries a civil penalty of up to $200, with seven calendar days to correct it or submit a repair plan. A second, uncorrected violation can reach $2,000, and each day it continues after that counts as its own separate offense under Section 1003.
Who enforces the electrical code in the unincorporated county?
The Department of Electrical Inspection, created under Section 301.1. Its code official is appointed by the county's chief appointing authority and can appoint deputies, technical officers, inspectors and plans examiners to help administer and enforce the code.

Sources & Official References

Other rules in Greenville County

All Greenville County rules

Compare Greenville County to another location·View the South Carolina building safety overview

Get notified when Electrical Permits in Greenville County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Greenville County