Key Facts
- Adopted code
- 2011 NEC + Florida Building Code (§ 6-135)
- Permit trigger
- Any alteration to an electrical system (§ 6-134(b)(2))
- Underground utilities
- 3-department review required (§ 6-134(b)(3))
- Fees
- Set by Board of County Commissioners resolution
- Work before permit
- 100% fee penalty (§ 6-134(d))
- Liability
- Owner and permit holder both responsible (§ 6-134(f))
Summary
Okaloosa County Code Section 6-135 adopts the Florida Building Code and the 2011 National Electrical Code by reference for the entire unincorporated permitting jurisdiction, along with their technical codes and appendices. A permit under Section 6-134(b)(2) is required before anyone alters, extends or replaces an electrical system, and starting work first draws a fee penalty.
Sec. 6-135. - Adoption of Florida Building Code, 2011 Electrical Code, and technical codes and appendices. There is hereby adopted by reference the Florida Building Code and the 2011 National Electrical Code, along with their associated technical codes, appendices, and ordinances not superseded by the Codes hereby adopted, including the non-technical and administrative chapters and requirements for all adopted codes. The edition of the Florida Building Code (all volumes) along with any other technical codes and appendices and ordinances approved by the Florida Building Code Commission, along with any local ordinances and codes not superseded by the codes adopted by the Florida Building Code Commission, shall take effect in the areas subject to the permitting jurisdiction of Okaloosa County on the effective date as established by the Florida Building Code Commission.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 23).
Full Breakdown
Section 6-135 adopts the Florida Building Code and the 2011 National Electrical Code 'by reference,' along with their associated technical codes, appendices and any local ordinances not superseded by the state-adopted codes; the whole package takes effect countywide on the date the Florida Building Code Commission sets. Section 6-134(b)(2) then triggers the permit requirement itself: a permit is required whenever an owner, agent or contractor wants to erect, enlarge, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system that the technical codes regulate.
Underground utility work is singled out for extra review in Section 6-134(b)(3), which routes each underground system through plan review, permitting and inspection by the Growth Management Department together with the county's Water and Sewer Department and Public Works Department. 721, Florida Statutes, plus non-county charges like credit-card fees. Anyone who starts wiring, panel or service work before the permit issues is charged double under Section 6-134(d): a penalty equal to 100 percent of the usual permit fee, on top of the fee itself. The property owner and the permit holder both stay on the hook for compliance with every adopted code under Section 6-134(f), regardless of who pulled the permit.
Violations & Fines
Starting electrical work before the permit is issued triggers a 100 percent penalty on top of the normal permit fee under Section 6-134(d). Beyond the fee penalty, unpermitted or noncompliant electrical work is a code violation: Section 114.1 of the county's Administrative Construction Code makes any violation of the adopted technical codes a second-degree misdemeanor, with each day the condition continues treated as a separate offense.
Frequently Asked Questions
What electrical code does Okaloosa County enforce in the unincorporated area?
Do I need a permit to replace a breaker panel or run new circuits?
What if my electrician starts before the permit comes through?
Sources & Official References
Other rules in Okaloosa County
Florida rules heatmap·Compare Okaloosa County to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.