Yavapai County, AZ Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Ordinance No. 2019-1 Sec. 110
Number of required stages
15 (Sec. 110.3.1-.15)
First stage
Footing inspection
Last stage
Final inspection, Sec. 110.3.15
Duty to call for inspection
Permit holder, Sec. 110.5
Re-inspection fee trigger
Work not ready or uncorrected

Summary

Yavapai County requires a set sequence of 15 inspections under Ordinance No. 2019-1 Sec. 110, from footing through final, before permitted work can be covered or occupied. Work must stay exposed until the building official signs off on each stage.

These county ordinances apply to unincorporated areas of Yavapai County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

110.3 - Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 110.3.1 through 110.3.15. 110.3.1 - Footing. Footing inspection shall be made after excavations for footings are complete and any required reinforcing steel is in place... 110.3.15 - Final inspection. Final inspection shall be made after the permitted work is complete and prior to occupancy.

Full Breakdown

3 of the Administrative Building Code lists 15 required inspection stages, Sec. 1 through Sec. 15: footing, stem wall/grout, reinforced masonry or ICF wall, concrete slab and under-floor, floodplain (for lots the Flood Control District flags), rough plumbing/mechanical/gas/electrical, roof nailing and braced wall panels, moisture barrier, framing and exterior lath, insulation, gypsum board, fire-resistant penetrations, special inspections under IBC Sec. 1704, other inspections the building official deems necessary, and finally Sec. 15 final inspection, made after all permitted work is complete. 1 requires the work to "remain accessible and exposed for inspection purposes until approved," and neither the building official nor the county is liable for the cost of uncovering work that was concealed too early.

5 puts the duty on the permit holder to call for each inspection and to provide site access; Sec. 6 bars any further work past the point of a given inspection until the building official approves it, and anything that fails must be corrected before it is covered again. 7 allows a re-inspection fee, set in the county's adopted fee schedule, whenever the work called for inspection is not ready or corrections were not made, though the first rejection on a job is not fee-bearing.

Re-inspection fees can also apply when the inspection card is not posted, approved plans are not on site, access is refused on the scheduled date, or the work deviates from approved plans.

Violations & Fines

Concealing work before the required inspection, or continuing construction past an inspection point without approval, is enforced as a building code violation under Sec. 114.1, a Class 2 misdemeanor. The Hearing Officer can order the covered work uncovered for inspection and, under Sec. 114.6, impose penalties up to $750 for an individual or $10,000 for a corporation per offense, with each day of a continuing violation a separate offense; re-inspection fees are billed separately under Sec. 110.7.

Frequently Asked Questions

What inspections does Yavapai County require during construction?
Fifteen separate stages under Sec. 110.3 of Ordinance No. 2019-1: footing, stem wall/grout, masonry or ICF wall, slab and under-floor, floodplain where applicable, rough plumbing/mechanical/gas/electrical, roof nailing and braced walls, moisture barrier, framing and exterior lath, insulation, gypsum board, fire-resistant penetrations, special inspections, other inspections the official requires, and final.
Who has to call for a Yavapai County building inspection?
The permit holder or an authorized agent, under Sec. 110.5. They must notify the building official when work is ready and give the inspector access to the site; failing to keep work exposed until it is approved can trigger a re-inspection fee or a code violation.
Can I keep building after one inspection passes?
Only up to the point covered by that inspection. Section 110.6 bars work beyond the point of each successive inspection until the building official approves it, and any portion that fails must be corrected and stay uncovered until re-inspected and authorized.

Sources & Official References

Other rules in Yavapai County

All Yavapai County rules

Compare Yavapai County to another location·View the Arizona building safety overview

Get notified when Building Inspections in Yavapai County, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.