Key Facts

Permit validity
3 years from issuance (IBC section 105.5)
Late renewal discount
Half-price if renewed within 1 year of expiration
Pre-permit application expiration
180 days, one 180-day extension allowed
Appeal deadline
15 days to Building Board of Appeals
Violation penalty
Misdemeanor under Idaho Code 18-113
Governing section
Ada County Code 7-2-4 (IBC section 105.5)

Summary

A building permit in unincorporated Ada County stays alive for three years from issuance. If the work isn't finished and the final inspection isn't performed and the project approved for occupancy within that three-year window, the permit expires automatically. Restarting after expiration means pulling a brand-new permit under section 7-2-4 of the county code.

City-specific rules exist: Boise has its own building inspections rules that differ from Ada County's county-level regulations. If you live in Boise, check the city-specific page instead.

105.5 Expiration. Add a second paragraph as follows: If work has not been completed, the final inspection performed and the project approved for occupancy or use within three (3) years from the date of such permit being issued, such permit shall expire by limitation and become null and void. Prior to work recommencing after the permit has expired, a new permit shall be obtained. The cost of the new permit, if obtained within one year of the original permit expiration, shall be one half (1/2) of the cost of a new permit for the remaining work required to complete the structure or project.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-15: Code current through: Ord. 1018, passed 3-24-2026).

Full Breakdown

Ada County adopted the 2018 International Building Code with local amendments at title 7, chapter 2, section 7-2-4 of the county code. 5, 'Expiration,' adds a second paragraph specific to Ada County: if work is not completed, the final inspection performed, and the project approved for occupancy or use within three years of the date the permit was issued, the permit expires by limitation and becomes null and void. Work cannot legally resume after that point without obtaining a brand-new permit. The county softens the cost of that reset only within a narrow window: a new permit obtained within one year of the original permit's expiration costs half of what a fresh permit for the remaining work would otherwise cost; wait past that one-year grace period and the full fee applies.

2, sets an earlier checkpoint before construction even starts: an application on which no permit is issued within 180 days of eligibility expires by limitation, though the building official can grant one 180-day extension on a showing that circumstances beyond the applicant's control caused the delay. 1. 1, and must be filed within 15 days of the decision per section 7-1-5(A).

Violations & Fines

Working past a stop-work order, or continuing construction under an expired or unpermitted permit, is a misdemeanor under section 7-2-12, punishable as provided in Idaho Code 18-113, with each day work continues after notice of violation charged as a separate offense. The county can also pursue an injunction or other court action under 7-2-12(B) to stop illegal construction. Investigative fees equal to the permit fee apply separately to any work performed before a permit was obtained.

Frequently Asked Questions

How long is my Ada County building permit good for?
Three years from the date it's issued. Under the county's amendment to IBC section 105.5, if the work isn't finished, the final inspection performed, and the project approved for occupancy within that three-year window, the permit expires automatically and becomes void, and any further work needs a brand-new permit.
What happens if my permit expires before I finish the project?
You have to obtain a new permit before resuming work. If you apply within one year of the original expiration, the county charges half the normal permit fee for the remaining work; wait longer than a year and you pay the full new-permit fee under section 105.5's second paragraph.
Can I appeal if the building official won't sign off on my final inspection?
Yes. Ada County Code 7-1-5 lets you appeal a building official's order, decision or determination to the Building Board of Appeals, but the application has to be filed with the Development Services Department within 15 days of that decision or it isn't accepted.

Sources & Official References

Other rules in Ada County

All Ada County rules

Compare Ada County to another location·View the Idaho building safety overview

Get notified when Building Inspections in Ada County, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.