Chico, CA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
CMC § 16.14.020
Inspection stages
5: foundation, slab, frame, lath, final
Request notice
24 hours before inspection, § 16.14.070
Steel/framing rule
Inspected before covered or concealed

Summary

Chico requires five building-official inspections during construction: foundation, slab/underfloor, frame, lath/wallboard, and final, before work may proceed past each stage.

A. Inspection by Building Official. The building official shall make the following inspections of all work on a building or structure for which a basic building permit is required... 1. Foundation Inspection... 3. Frame Inspection. A frame inspection shall be made after the roof, all framing, fireblocking, and bracing are in place; all pipes, chimneys, and vents are complete... 5. Final Inspection. A final inspection shall be made after finish grading on the building is completed and ready for occupancy.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Supplement contains local legislation current through: Codified Resolution No. 53-26, adopted 7-14-26 and Ordinance No. 2622, adopted 6-2-26).

Full Breakdown

Under Chico Municipal Code § 16.14.020, the building official inspects permitted work at fixed stages and must approve each before covered work continues: a foundation inspection after trenches are excavated and forms erected; a slab/underfloor inspection before concrete or floor sheeting is placed; a frame inspection once roof framing, fireblocking, bracing, and rough electrical/plumbing/HVAC are in place; a lath or wallboard inspection before plaster or taping; and a final inspection after finish grading, when the building is ready for occupancy. Reinforcing steel or structural framework must be inspected before it is covered. Fire and life-safety inspections run separately under the fire chief for most non-single-family occupancies.

Violations & Fines

Covering or concealing work before the required stage inspection is approved violates § 16.14.010; the building official may order the work exposed for inspection, and further construction is barred until it passes.

Frequently Asked Questions

What are the five required building inspections in Chico?
Foundation, concrete slab/underfloor, frame, lath or wallboard, and final: each must be approved before work moves to the next stage, per CMC § 16.14.020.
How much notice does a Chico permit holder give before an inspection?
Requests must be made at least 24 hours before the desired inspection time unless the building official waives it for good cause, per CMC § 16.14.070.

Sources & Official References

Other rules in Chico

All Chico rules

California rules heatmap·Compare Chico to another location·View the California building safety overview

Get notified when Building Inspections in Chico, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.