Yavapai County, AZ Building Safety: Building Inspections (2026)
Key Facts
- Governing section
- Ordinance No. 2019-1 Sec. 110
- Number of required stages
- 15 (Sec. 110.3.1-.15)
- First stage
- Footing inspection
- Last stage
- Final inspection, Sec. 110.3.15
- Duty to call for inspection
- Permit holder, Sec. 110.5
- Re-inspection fee trigger
- Work not ready or uncorrected
Summary
Yavapai County requires a set sequence of 15 inspections under Ordinance No. 2019-1 Sec. 110, from footing through final, before permitted work can be covered or occupied. Work must stay exposed until the building official signs off on each stage.
110.3 - Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 110.3.1 through 110.3.15. 110.3.1 - Footing. Footing inspection shall be made after excavations for footings are complete and any required reinforcing steel is in place... 110.3.15 - Final inspection. Final inspection shall be made after the permitted work is complete and prior to occupancy.
Full Breakdown
3 of the Administrative Building Code lists 15 required inspection stages, Sec. 1 through Sec. 15: footing, stem wall/grout, reinforced masonry or ICF wall, concrete slab and under-floor, floodplain (for lots the Flood Control District flags), rough plumbing/mechanical/gas/electrical, roof nailing and braced wall panels, moisture barrier, framing and exterior lath, insulation, gypsum board, fire-resistant penetrations, special inspections under IBC Sec. 1704, other inspections the building official deems necessary, and finally Sec. 15 final inspection, made after all permitted work is complete. 1 requires the work to "remain accessible and exposed for inspection purposes until approved," and neither the building official nor the county is liable for the cost of uncovering work that was concealed too early.
5 puts the duty on the permit holder to call for each inspection and to provide site access; Sec. 6 bars any further work past the point of a given inspection until the building official approves it, and anything that fails must be corrected before it is covered again. 7 allows a re-inspection fee, set in the county's adopted fee schedule, whenever the work called for inspection is not ready or corrections were not made, though the first rejection on a job is not fee-bearing.
Re-inspection fees can also apply when the inspection card is not posted, approved plans are not on site, access is refused on the scheduled date, or the work deviates from approved plans.
Violations & Fines
Concealing work before the required inspection, or continuing construction past an inspection point without approval, is enforced as a building code violation under Sec. 114.1, a Class 2 misdemeanor. The Hearing Officer can order the covered work uncovered for inspection and, under Sec. 114.6, impose penalties up to $750 for an individual or $10,000 for a corporation per offense, with each day of a continuing violation a separate offense; re-inspection fees are billed separately under Sec. 110.7.
Frequently Asked Questions
What inspections does Yavapai County require during construction?
Who has to call for a Yavapai County building inspection?
Can I keep building after one inspection passes?
Sources & Official References
Other rules in Yavapai County
Compare Yavapai County to another location·View the Arizona building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.