Ascension Parish, LA Building Safety: Building Inspections (2026)
Key Facts
- Enforcing agency
- Ascension Parish Building Official
- Required inspection stages
- footing, slab, framing, energy, final
- Re-inspection fee
- $30.00 per failed craft inspection
- Flood-area requirement
- lowest-floor elevation filed before occupancy
Summary
Any construction that needed a permit in unincorporated Ascension Parish has to pass the Building Official's inspections before work is covered up. Ascension Parish Code § 6-9 lists the required stages: footing and foundation, concrete slab or under-floor, framing, energy efficiency, and a final inspection, plus separate inspections for mechanical, plumbing, electrical and gas systems.
900. General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... 918. Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official.
Full Breakdown
Section 6-9(900) makes any permitted construction or work subject to inspection by the Building Official, and requires it to remain accessible and exposed for inspection purposes until approved. The code lays out the sequence: a footing and foundation inspection under section 903 happens after excavation is complete and reinforcing steel is placed; a concrete slab and under-floor inspection under section 904 happens after in-slab reinforcing and service equipment are in place but before concrete is poured or subfloor installed; and a frame inspection under section 905 happens after the roof deck, framing, fireblocking and bracing are up and rough electrical, plumbing and HVAC work is approved.
Section 907 requires energy efficiency inspections covering envelope insulation R- and U-values, fenestration, duct system R-value, and HVAC and water-heating equipment efficiency. Mechanical, plumbing, electrical and gas systems each get their own inspection under sections 912 through 915. A final inspection under section 910 happens after all permitted work is complete, and section 911 requires flood-hazard-area projects to submit lowest-floor elevation documentation before a certificate of occupancy issues. Section 917 puts the burden on the permit holder to notify the Building Official when work is ready, and section 918 bars any work from proceeding beyond the point indicated in each successive inspection until the Building Official signs off on that stage.
Violations & Fines
Covering or concealing work before the required inspection is approved violates section 6-9(918): any portion that fails to comply shall be corrected and shall not be covered or concealed until authorized by the Building Official. A failed or missed inspection also triggers the section 6-8(801)(8) re-inspection fee of $30.00 for each subsequent rejected inspection per craft, payable before utilities are authorized or a certificate of occupancy issues.
Frequently Asked Questions
What inspections does Ascension Parish require during construction?
Can I cover up framing before the inspector signs off?
What if my project fails an inspection?
Sources & Official References
Other rules in Ascension Parish
Compare Ascension Parish to another location·View the Louisiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.