Key Facts

Building stages
Foundation, framing, final
Trade inspections
Underground, rough-in, final
Duty
Keep work exposed until approved
Applies
Unincorporated DeKalb permitted work

Summary

DeKalb County requires staged inspections for permitted work, including foundation, framing and final inspections for buildings plus rough-in inspections for electrical, plumbing, mechanical and gas systems.

These county ordinances apply to unincorporated areas of DeKalb County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The building official, upon notification, shall make the inspections set forth as follows:(1)Building.(A)Foundation and slab inspection: To be made after trenches are excavated, forms are erected, and reinforcement is installed but before concrete is put in place. The appropriate silt and erosion control measures must be in place and functional.(B)Damproofing inspection: To be made prior to backfill of crawl space or basement foundation walls.(C)Pre-cladding/frame inspection: To be made after the roof, wall bracing, windows, doors and moisture barrier are installed and prior to placement of exterior cladding. Rough inspections on trades need not be complete for pre-cladding inspection.(D)Frame/insulation inspection: To be made after wiring, piping, chimneys, duct and vents to be concealed are in place and all rough inspections approved, fire blocking is in place and the insulation in walls and inaccessible ceilings is installed. Insulation values must meet documents submitted with permit application.(E)Final inspection: To be made after the building or structure is completed in compliance with this Code prior to issuance of the certificate of occupancy.

Full Breakdown

Section 7-34(c) of the DeKalb County Code lists the required inspections for permitted construction. Building work is inspected at the foundation/slab, damproofing, pre-cladding, frame/insulation and final stages, with parallel underground, rough-in and final inspections for electrical, plumbing, mechanical and gas systems. Work must stay accessible for inspection until approved, and the building official can require additional inspections. A final building inspection happens after construction is complete and before a certificate of occupancy is issued. This applies to permitted work in unincorporated DeKalb County.

Violations & Fines

Covering or concealing work before the required inspection is approved is a violation, and the building official can require it uncovered for inspection at the owner's expense.

Frequently Asked Questions

What inspections does DeKalb County require during construction?
Staged inspections including foundation/slab, framing and final for buildings, plus underground, rough-in and final inspections for electrical, plumbing, mechanical and gas work, per § 7-34(c).
Can I cover framing before it's inspected?
No, § 7-34(a) requires work to stay accessible and exposed for inspection until the building official approves it.

Sources & Official References

Other rules in DeKalb County

All DeKalb County rules

Compare DeKalb County to another location·View the Georgia building safety overview

Get notified when Building Inspections in DeKalb County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.