Key Facts
- Inspector response time
- within 8 working hours of request
- Enforcing office
- Building Inspection Division, Code Enforcement
- Contractor duty
- must call before covering work
- Final step
- certificate of approval, EMC 15.05.130
Summary
Evansville's Building Inspection Division must inspect permitted work within eight working hours of a contractor's request, before it can be covered, under the city's building code inspection process.
All work which requires a permit under EMC 15.05.420(A) shall be inspected by the Building Inspection Division of the Department of Code Enforcement. Work which will be covered shall be inspected prior to installing any material which would not allow a visible inspection. The contractor for the trade of the affected installation shall contact the Building Inspection Division and request an inspection prior to work being covered. Any contractor failing to request inspection and any contractor covering work before an inspection is in violation of this chapter and shall be subject to the penalties of EMC 15.05.520. If, in the opinion of the Building Commissioner, the covered work cannot otherwise be deemed safe and in compliance with applicable codes, the contractor responsible for covering work not inspected shall uncover any and all areas as directed by the Building Commissioner. The Inspector shall inspect the installation as soon as possible after receiving the request but in no case shall it be more than eight working hours from the time the call is received. If any inspection is not approved by the Inspector, the contractor may request and shall be provided by the department within eight working hours the specific code, chapter and section that has been violated. This section may be modified by the Building Commissioner under emergency conditions.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance G-2026-12, passed June 22, 2026).
Full Breakdown
Evansville's Building Inspection Division, part of the Department of Code Enforcement, inspects all work that requires a permit before it gets covered up: contractors must call the Division and request an inspection before installing any material that would hide the work from view. Once a request comes in, the inspector has no more than eight working hours to inspect. If the work isn't approved, the department must, within that same eight-hour window, give the contractor the specific code chapter and section violated. Skipping the inspection call, or covering work before it's inspected, is itself a code violation. The process continues through re-inspection of flagged issues (EMC 15.05.110) up to a final certificate of approval (EMC 15.05.130).
Violations & Fines
Failing to call for inspection before covering work, or covering work before an inspector signs off, is a Title 15 violation subject to the penalties in EMC 15.05.520.
Frequently Asked Questions
How fast must Evansville inspect building work after it's requested?
What happens if a contractor covers work before inspection in Evansville?
Sources & Official References
Other rules in Evansville
Compare Evansville to another location·View the Indiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.