Irondequoit, NY Building Safety: Building Inspections (2026)
Key Facts
- Required inspection stages
- Eleven listed in § 98-11(G), ending with final inspection
- Who requests each inspection
- Owner, agent or permit holder
- Inspectors
- Building Inspector and Fire Marshal
- Building permit void if work not started
- Within six months of issuance
- Maximum permit term
- One year, plus no more than two ninety-day extensions
- Entry refused
- Warrant can be sought from any court of competent jurisdiction
Summary
In the Town of Irondequoit, Monroe County, New York, Code § 98-11(G) keeps work exposed until the Building Inspector accepts it and lists eleven inspection stages, from the pre-permit site visit through footings, framing and building systems to the final inspection. The permit holder must call for each stage.
G. Required inspections. Work shall remain accessible and exposed until inspected and accepted by the Building Inspector or other authorized inspector. The permit holder shall notify the Building Inspector when any work described below is ready for inspection. Inspections and tests of the following will be made, where applicable: (1) Work site prior to the issuance of a permit. (2) Footings and foundation. (3) Preparation for concrete slab. (4) Framing. (5) All building systems, including, for example, electrical, plumbing, fuel gas and HVAC, including underground and rough-in. (6) Fire-resistant construction. (7) Fire-resistant penetrations. (8) Solid-fuel-burning and fuel-gas-burning heating appliances, chimneys, flues or gas vents. (9) Energy Code compliance. (10) Final inspection after all work authorized by the building permit has been completed. (11) Such other inspections as may be deemed appropriate by the inspector or as may be required by the Uniform Code.
Full Breakdown
Chapter 98 spells out inspection stages in § 98-11(G). Work stays accessible and exposed until the Building Inspector or another authorized inspector accepts it, and the permit holder tells the Building Inspector when each listed stage is ready. The eleven printed stages start with the work site before a permit issues, then footings and foundation, preparation for concrete slab, framing, all building systems including electrical, plumbing, fuel gas and HVAC with underground and rough-in work, fire-resistant construction, fire-resistant penetrations, solid-fuel-burning and fuel-gas-burning heating appliances, chimneys, flues or gas vents, Energy Code compliance, and the final inspection. A catch-all covers other inspections the inspector deems appropriate or the Uniform Code requires.
After each inspection, § 98-11(H) requires the work to be noted as satisfactory or the permit holder to be told how it fails to comply with the Uniform Code. Failing work stays exposed until it is corrected, reinspected and found satisfactory. Section 98-45 puts the burden of calling for inspections on the owner or the owner's agent, who notifies the Fire Marshal or the Building Inspector; the advance time and acceptable means of notification follow the requirements of those officials or established policy. A missed required inspection can lead to rejection of the work and, where deemed necessary, an order to expose the work for inspection.
The Fire Marshal and Building Inspector can enter any building or premises within the Town of Irondequoit at all reasonable hours to inspect for compliance with the chapter and the Uniform Code. If entry is denied, application can be made to any court of competent jurisdiction for a warrant. Under § 98-11(F), applying for or accepting a permit counts as consent to inspections, and refusing an inspection of the premises and records justifies revocation or suspension of the permit.
Timing rules frame the process. A building permit becomes void if work does not start within six months of issuance (§ 98-13(C)), and § 98-11(E) caps a permit at one year with no more than two ninety-day extensions. The Building Inspector issues a certificate of occupancy only after final inspection shows the work fully completed (§ 98-16).
Violations & Fines
Failing to notify the Fire Marshal or Building Inspector for a required inspection can lead to rejection of the work and an order to expose it under § 98-45(B). Work found out of compliance must stay exposed until reinspected. Refusing entry for an inspection justifies permit revocation or suspension under § 98-11(F). Violations of Chapter 98 are punishable under § 98-51 by a fine of not more than $1,000 per day of violation or imprisonment not exceeding one year, or both.
Frequently Asked Questions
Which inspections does the Town of Irondequoit require during construction?
Who has to schedule inspections in the Town of Irondequoit?
What happens if work fails an inspection in the Town of Irondequoit?
Can Irondequoit inspectors enter my property?
Sources & Official References
Other rules in Irondequoit
New York rules heatmap·Compare Irondequoit to another location·View the New York building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Monroe County handle building inspections.