Macon County, IL Building Safety: Building Inspections (2026)
Key Facts
- Concealment inspection
- required before wiring is covered
- Final inspection
- required before certificate of occupancy
- Reinspection fee
- $50 per failed inspection call
- Who requests
- electrical contractor gives timely notice
- Enforcement
- County Electrical Commission can revoke permit
Summary
Electrical work permitted under Macon County's Electrical Code must be inspected before it's covered up and again for final approval before a certificate of occupancy can issue. Contractors must request inspections with timely notice, and an inspection call the site isn't ready for triggers a $50 reinspection fee under § 150.13.
All electrical wiring installed under a permit issued as herein provided must be inspected before being concealed and must have a final approved inspection before the certificate of occupancy is eligible for issuance. ... It is the responsibility of the electrical contractor, or those making electrical installations or alterations, to give timely notice requesting inspections. ... Failure to call for final electrical inspections before structures are occupied or after job completion will be cause for the Control Authority to submit the case before the Electrical Commission for possible action. ... A reinspection fee of $50 shall be assessed against the applicant for an electrical permit who has requested an inspection which cannot be completed and/or approved by the Control Authority for any of the following reasons: (A) The work for which the inspection has been requested is not installed or completed to the extent that an inspection can be made;
Full Breakdown
Macon County's inspection process for electrical work runs on two checkpoints under § 150.11: an in-progress inspection before any wiring is concealed behind walls or ceilings, and a final approved inspection before the certificate of occupancy can be issued. It is the electrical contractor's job, or that of whoever made the installation, to call the Control Authority with timely notice requesting each inspection; the Control Authority has discretion to push the inspection date back if scheduling requires it. Skipping the final inspection before a structure is occupied, or after the job is otherwise done, is not a paperwork lapse the county lets slide: the Control Authority can bring the case to the County Electrical Commission, which has the power to revoke the permit or withhold approval of the work outright if it finds a false statement or misrepresentation in the application, plans, or specifications the permit was based on.
Calling for an inspection the site isn't ready for costs money. Under § 150.13, the county charges a $50 reinspection fee whenever an inspection is requested but cannot be completed or approved, whether because the work isn't far enough along to inspect, the system turns up more than three code violations, the inspector cannot get onto the site at the requested time, or previously flagged violations were never fixed. Fees are billed by certified mail and can be appealed to the County Board before payment is due.
Violations & Fines
Skipping a required inspection, especially the final inspection before a structure is occupied, lets the Control Authority refer the case to the County Electrical Commission, which can revoke the permit or withhold approval of the work; requesting an inspection the site isn't ready for costs a $50 reinspection fee under § 150.13, and repeat unresolved violations can leave that fee withheld from a certificate of occupancy.
Frequently Asked Questions
When does Macon County require an electrical inspection?
What if the inspector shows up and the work isn't ready?
Can Macon County revoke my electrical permit over an inspection issue?
Sources & Official References
Other rules in Macon County
Compare Macon County to another location·View the Illinois building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.