Key Facts

Enforcing agency
Ascension Parish Building Official
Required inspection stages
footing, slab, framing, energy, final
Re-inspection fee
$30.00 per failed craft inspection
Flood-area requirement
lowest-floor elevation filed before occupancy

Summary

Any construction that needed a permit in unincorporated Ascension Parish has to pass the Building Official's inspections before work is covered up. Ascension Parish Code § 6-9 lists the required stages: footing and foundation, concrete slab or under-floor, framing, energy efficiency, and a final inspection, plus separate inspections for mechanical, plumbing, electrical and gas systems.

These county ordinances apply to unincorporated areas of Ascension Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

900. General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... 918. Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official.

Full Breakdown

Section 6-9(900) makes any permitted construction or work subject to inspection by the Building Official, and requires it to remain accessible and exposed for inspection purposes until approved. The code lays out the sequence: a footing and foundation inspection under section 903 happens after excavation is complete and reinforcing steel is placed; a concrete slab and under-floor inspection under section 904 happens after in-slab reinforcing and service equipment are in place but before concrete is poured or subfloor installed; and a frame inspection under section 905 happens after the roof deck, framing, fireblocking and bracing are up and rough electrical, plumbing and HVAC work is approved.

Section 907 requires energy efficiency inspections covering envelope insulation R- and U-values, fenestration, duct system R-value, and HVAC and water-heating equipment efficiency. Mechanical, plumbing, electrical and gas systems each get their own inspection under sections 912 through 915. A final inspection under section 910 happens after all permitted work is complete, and section 911 requires flood-hazard-area projects to submit lowest-floor elevation documentation before a certificate of occupancy issues. Section 917 puts the burden on the permit holder to notify the Building Official when work is ready, and section 918 bars any work from proceeding beyond the point indicated in each successive inspection until the Building Official signs off on that stage.

Violations & Fines

Covering or concealing work before the required inspection is approved violates section 6-9(918): any portion that fails to comply shall be corrected and shall not be covered or concealed until authorized by the Building Official. A failed or missed inspection also triggers the section 6-8(801)(8) re-inspection fee of $30.00 for each subsequent rejected inspection per craft, payable before utilities are authorized or a certificate of occupancy issues.

Frequently Asked Questions

What inspections does Ascension Parish require during construction?
Section 6-9 requires footing and foundation, concrete slab or under-floor, framing, energy efficiency and final inspections, plus separate mechanical, plumbing, electrical and gas inspections as those systems are installed.
Can I cover up framing before the inspector signs off?
No. Section 6-9(918) bars work from proceeding past an inspected stage until the Building Official approves it, and any noncompliant work must stay uncovered until it is corrected and authorized.
What if my project fails an inspection?
You pay a $30.00 re-inspection fee under § 6-8(801)(8) for each subsequent failed inspection per craft, and that fee must be paid before utilities are authorized or a certificate of occupancy is issued.

Sources & Official References

Other rules in Ascension Parish

All Ascension Parish rules

Compare Ascension Parish to another location·View the Louisiana building safety overview

Get notified when Building Inspections in Ascension Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.