Kent County, DE Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Enforcing office
Dept. of Planning Services building official
Required stages
Footing, slab, frame, energy, waterproofing, final
Flood-zone step
Lowest-floor elevation certified before vertical work
Notification duty
Permit holder must request each inspection
First-offense fine
$100 mandatory minimum

Summary

Kent County's building official must inspect permitted work at set stages, footing and foundation, concrete slab, framing, energy efficiency and a final inspection, before work can proceed or a certificate of occupancy issues. Permit holders must notify the county when work is ready and keep it accessible until each stage is approved.

These county ordinances apply to unincorporated areas of Kent County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 105-9. Inspections. ... C. Required inspections. The building official, upon notification, shall make the inspections set forth below: (1) Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place... (4) Frame inspection. Framing inspections shall be made after the roof deck or sheathing and all framing, fire-blocking and bracing are in place; pipes, chimneys and vents to be concealed are complete; and the rough electrical, plumbing, heating wires, pipes and ducts are approved. ... (6) Energy efficiency inspections. Inspections shall be made to determine compliance with the current state-adopted International Energy Conservation Code... (11) Final inspection. The final inspection shall be made after all work required by the building permit is completed and all other applicable agency approvals have been acquired.

Full Breakdown

C sets the required inspection stages for any construction needing a permit. A footing and foundation inspection happens after excavation is complete and reinforcing steel is placed (C(1)); a concrete slab and under-floor inspection occurs after in-slab reinforcing and utilities are set but before concrete is poured or subfloor installed (C(2)); in flood hazard areas, an elevation certification for the lowest floor must be submitted before further vertical construction (C(3)); a frame inspection follows once the roof deck, framing, fire-blocking, bracing and rough electrical, plumbing and mechanical work are in place and approved (C(4)); fire- and smoke-resistant penetrations must stay exposed until inspected (C(5)); and energy efficiency inspections check envelope insulation, fenestration, duct R-values and HVAC/water-heating equipment, capped off with an energy compliance sticker in the electrical panel before a certificate of occupancy issues (C(6)).

Waterproofing inspections are required for any dwelling with a basement before it is backfilled (C(10)), and a final inspection closes out the permit once all required work and other agency approvals are complete (C(11)). The building official can also require other inspections needed to confirm code compliance (C(7)) and special inspections under IBC Chapter 17 (C(8)). F bars proceeding past any inspected stage without approval, requiring correction of any noncompliant work before it is covered or concealed.

Violations & Fines

Covering or concealing work before it passes the required inspection, or proceeding past an inspection stage without approval, is a violation under § 105-14.D, fined at $100 for a first offense, $250 for a second, $500 for a third, and $1,000 to $10,000, or up to 10 days' imprisonment, for a fourth or later offense, with the $100 minimum mandatory and each day of the violation a separate offense (§ 105-14.E). The building official may issue a stop-work order under § 105-15 for work performed past a failed or skipped inspection, carrying the same escalating fines for continued work.

Frequently Asked Questions

What inspections does Kent County require during construction?
Section 105-9.C lists footing and foundation, concrete slab, framing, fire- and smoke-resistant penetrations, energy efficiency, waterproofing for basements, and a final inspection, plus a lowest-floor elevation check in flood hazard areas before vertical construction continues.
Who has to schedule building inspections in Kent County?
The permit holder or their authorized agent must notify the building official when work is ready for inspection under § 105-9.E and must keep the work accessible; the building official then either approves the stage or identifies what fails to comply.
Can I keep building past a failed Kent County inspection?
No. Section 105-9.F bars work from proceeding past any inspected stage without the building official's approval, and noncompliant portions must be corrected and cannot be covered or concealed until authorized.

Sources & Official References

Other rules in Kent County

All Kent County rules

Compare Kent County to another location·View the Delaware building safety overview

Get notified when Building Inspections in Kent County, DE changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.