Skip to main content
CityRuleLookup

Beaufort County, SC Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Department created by
§ 74-67
First reinspection
Free
Extra reinspection fee
$25.00
Appeals board meeting deadline
Within 30 days of notice
Permit refund window
Void after 6 months unstarted

Summary

Beaufort County's building official rechecks failed work for free once, under Code of Ordinances § 74-97(f), but charges $25.00 for each additional reinspection caused by a wrong address, condemned or faulty work, uncorrected repairs, or work that was not ready when the inspector arrived. The department of building inspections created by § 74-67 administers the technical codes for the unincorporated county.

These county ordinances apply to unincorporated areas of Beaufort County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

If the building official or his duly authorized representative shall, upon his inspection after the completion of the work or apparatus, find the work or apparatus does not conform to or comply with the applicable provisions of this Code, he shall notify the contractor, indicating the corrections to be made, and then he shall again inspect the work or apparatus without further charge. However, when extra inspections are due to any of the following reasons, a charge of $25.00 shall be made for each reinspection:(1)Wrong address.(2)Condemned work, resulting from faulty work.(3)Repairs or corrections not made when inspections are called.(4)Work not ready for inspection when called.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 55 Update 1 | Community Development Code: Supplement 16).

Full Breakdown

Section 74-67 creates the department of building inspections and makes its building official responsible for administering and enforcing the technical codes chapter, serving as secretary of the construction board of adjustments and appeals, and reporting as a county department head through the county administrator. 00 each, and every reinspection fee must be paid before any further inspection proceeds. Appeals from the building official go to the construction board of adjustments and appeals, which under § 74-32(a) must meet within 30 calendar days after receiving notice of appeal, and § 74-32(b) requires the board to reach a written decision without unreasonable delay, filed publicly and mailed to the appellant, with every decision final subject to court remedies.

Violations & Fines

Fees are mandatory before any inspection work proceeds: § 74-96(b) bars issuing or amending a permit until fees are paid, doubling the fee if work starts before the permit issues, and § 74-97(f) bars further inspection until outstanding reinspection fees are paid. Underlying noncompliance with the adopted codes remains a misdemeanor under § 74-63, fined up to $100.00 or up to 30 days in jail, each day a separate offense.

Frequently Asked Questions

Is the first building reinspection free in Beaufort County?
Yes. Under § 74-97(f), if the building official finds work does not conform to code, he notifies the contractor of the needed corrections and reinspects once at no charge. Only extra reinspections caused by a wrong address, faulty work, uncorrected repairs or work not being ready trigger the $25.00 fee.
Who runs building inspections in unincorporated Beaufort County?
The department of building inspections, created under § 74-67, administers and enforces the technical codes chapter. Its building official also serves as secretary of the construction board of adjustments and appeals and reports as a county department head through the county administrator.
How long does the appeals board take to hear a building permit appeal?
Under § 74-32(a), the construction board of adjustments and appeals must meet within 30 calendar days after receiving notice of appeal, and § 74-32(b) requires it to reach a written decision without unreasonable delay, with the decision filed publicly and posted for two weeks.

Sources & Official References

Other rules in Beaufort County

All Beaufort County rules

Compare Beaufort County to another location·View the South Carolina building safety overview

Get notified when Building Inspections in Beaufort County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.