Key Facts

Governing section
Wayne County Code § 14-64
First inspection stage
Footing, before concrete pour
Final stage
Final inspection before certificate of occupancy
Occupancy rule
No occupancy without certificate of occupancy
Max penalty
$500 fine, separate offense per day

Summary

In unincorporated Wayne County, permit holders must call the inspection department for approval at each construction stage, from footing and foundation through framing and insulation, before work continues. A final inspection follows completed construction, and no building may be occupied until the inspection department issues a certificate of occupancy under Sec. 14-64.

These county ordinances apply to unincorporated areas of Wayne County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

All holders of permits, or their agents, shall notify the inspection department and the appropriate inspector at each of the following stages of construction so that approval may be given before work is continued:(1)Footing. Before concrete is poured into footing with grade markers in place and any reinforcing steel and supports if required. (No wood grade markers.)(2)Foundation. Foundation with bolts as per code; 12 inches from corners and four feet on center before dirt is around piers and over footing. ... (7)Final inspection. General contractor and/or permit holder to call for final inspection. When all construction work is completed with vapor barrier installed under home and ready for certificate of occupancy. ... No new building or part thereof shall be occupied, and no addition or enlargement of any existing building shall be occupied, and no existing building after being altered or moved shall be occupied, and no change of type of occupancy shall be made in any existing building or part thereof, until the inspection department has issued a certificate of occupancy therefor.

Full Breakdown

Sec. 14-64 lays out the stage-by-stage inspection sequence every Wayne County permit holder must follow. Before concrete is poured into footings, grade markers, reinforcing steel and supports must be in place (wood grade markers are not allowed). The foundation stage requires bolts installed per code, spaced 12 inches from corners and four feet on center, checked before dirt is backfilled around piers and over the footing; concrete-slab work has its own pre-pour plumbing and vapor-barrier checks. Floor framing is inspected before sheathing goes down, once the crawl space is cleared of vegetation and debris, followed by exterior sheathing and nailing, then rough-in framing, plumbing, mechanical and electrical work with holes caulked before insulation.

Insulation itself is checked before sheetrock or paneling goes up. The general contractor or permit holder must then call for a final inspection once all work, including the under-home vapor barrier, is complete and ready for a certificate of occupancy. Sec. 14-64(b) requires the holder to notify the inspection department before covering any completed work; concealed work must be uncovered on request for inspection, and failing to call for inspections or proceeding without approval at each stage is itself a violation of the article. Sec.

14-64(d) bars occupancy of any new, altered, enlarged or converted building until the inspection department issues a certificate of occupancy, though a temporary certificate can cover a portion safely ready for use before the whole building is finished. Sec. 14-64(e) also lets inspectors withhold a certificate of occupancy, via a stop order, if a setback violation surfaces before it is resolved.

Violations & Fines

Skipping a required inspection call, or continuing work without the inspector's approval at any stage, is a violation of Article III. Under Sec. 14-129, willful failure to comply with an inspector's order is a class 3 misdemeanor carrying a fine of up to $500.00, with each day of continued noncompliance treated as a separate offense; the inspector may also issue a stop order under Sec. 14-66(c) halting hazardous or unapproved work.

Frequently Asked Questions

What are the required Wayne County building inspection stages?
Sec. 14-64 lists footing, foundation, floor framing, sheathing, rough-in framing (plumbing, mechanical and electrical), insulation, and a final inspection, in that order. The permit holder must notify the inspection department before each stage is covered so the appropriate inspector can approve it before work continues.
Can I move into a new home before the final inspection?
No. Sec. 14-64(d) bars occupying any new building, addition or altered structure until the inspection department issues a certificate of occupancy, though a temporary certificate can be issued for a portion of the building that is safely ready before the whole project is finished.
What happens if concealed work was not inspected first?
Sec. 14-64(b) requires any work concealed before inspection and approval to be uncovered at the inspector's request and put back in condition for proper inspection; failing to call for an inspection or proceeding without approval is itself a violation of Article III.

Sources & Official References

Other rules in Wayne County

All Wayne County rules

Compare Wayne County to another location·View the North Carolina building safety overview

Get notified when Building Inspections in Wayne County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.