Montgomery County, MD Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Notice before start of work
24 hours
Notice before covering footings/reinforcement
24 hours
First approved inspection deadline
12 months from permit issuance
Second approved inspection deadline
14 months from permit issuance
Enforcing agency
Dept. of Permitting Services

Summary

Montgomery County requires 24 hours' notice before starting permitted work and before covering up footings, reinforcement, or fire stopping.

City-specific rules exist: Rockville has its own building inspections rules that differ from Montgomery County's county-level regulations. If you live in Rockville, check the city-specific page instead.

At least twenty-four (24) hours' notice of start of work under a building permit shall be given to the department unless this requirement is waived in the building permit. At least twenty-four (24) hours' notice shall be given the department for inspection of footings, concrete reinforcement, fire stopping and similar details before they are covered up.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-90: Montgomery County Code contains legislation effective through May 7, 2026 | Zoning Updated Effective: April 13, 2026 | COMCOR Regulations effective as of July 1, 2026).

Full Breakdown

Under County Code Section 8-25(h), anyone working under a building permit must give the Department of Permitting Services at least 24 hours' notice before starting work, unless the permit waives that requirement. The same 24-hour notice applies before footings, concrete reinforcement, fire stopping, and similar details are covered up, so the Department can inspect them first. Separately, Section 8-25(b) ties permit validity to inspections: a permit becomes invalid if no approved inspection is logged in the Department's inspection history file within 12 months of issuance and a second approved inspection within 14 months, or if work is abandoned for 6 months.

Violations & Fines

Covering work before the required inspection, or missing the 12/14-month inspection milestones, can invalidate the permit and force re-application.

Frequently Asked Questions

How much notice do I need to give before an inspection?
At least 24 hours, both to start work and before covering footings, reinforcement, or fire stopping, unless the permit waives it.
What happens if I miss the inspection deadlines?
The permit becomes invalid if no approved inspection is recorded within 12 months, and a second within 14 months, of issuance.

Sources & Official References

Other rules in Montgomery County

All Montgomery County rules

Compare Montgomery County to another location·View the Maryland building safety overview

Get notified when Building Inspections in Montgomery County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.